1.

MULTIPLE SELECT QUESTION

45 sec • 1 pt

What is the purpose of the Sprint Planning meeting in Scrum?

To review the progress of the current Sprint

To plan and select items from the Product Backlog for the upcoming Sprint

To prioritize items in the Product Backlog

To retrospect on the previous Sprint

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Who is responsible for creating the Product Backlog in Scrum?

The Scrum Master

The Development Team

The Product Owner

The stakeholders

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the recommended duration for a Sprint in Scrum?

1 week

2 weeks

3 weeks

4 weeks

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Who is responsible for estimating the effort required to complete each Product Backlog item?

The Scrum Master

The Development Team

The Product Owner

The stakeholders

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the purpose of the Sprint Review meeting in Scrum?

To review the progress of the current Sprint

To plan and select items from the Product Backlog for the upcoming Sprint

To retrospect on the previous Sprint

To demonstrate and get feedback on the completed work in the current Sprint

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the purpose of the Sprint Retrospective meeting in Scrum?

To review the progress of the current Sprint

To plan and select items from the Product Backlog for the upcoming Sprint

To retrospect on the previous Sprint

o demonstrate and get feedback on the completed work in the current Sprint

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the main advantage of using Planning Poker for estimation in Scrum?

It provides a more accurate estimate

It saves time

It is easier to use than other estimation techniques

It is more fun than other estimation techniques

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?