УБ21-1 (2)

УБ21-1 (2)

University

47 Qs

quiz-placeholder

Similar activities

Interior Design Review of 1.01-2.02

Interior Design Review of 1.01-2.02

8th Grade - University

43 Qs

Unit 6 Public Policy Quiz

Unit 6 Public Policy Quiz

University

49 Qs

G&L Chapter 13, "Instructions," pgs. 227-239

G&L Chapter 13, "Instructions," pgs. 227-239

University

49 Qs

УБ21-3

УБ21-3

University

45 Qs

УБ21-1

УБ21-1

University

44 Qs

[B2B MUL] CHAP 11

[B2B MUL] CHAP 11

University

44 Qs

SEMI sa SCM

SEMI sa SCM

University

50 Qs

UTEP PHARM ISBP study pain Physiology and pathophysiology

UTEP PHARM ISBP study pain Physiology and pathophysiology

University - Professional Development

46 Qs

УБ21-1 (2)

УБ21-1 (2)

Assessment

Quiz

Specialty

University

Hard

Created by

Елизавета Кожаткина

Used 1+ times

FREE Resource

47 questions

Show all answers

1.

MULTIPLE SELECT QUESTION

45 sec • 1 pt

Tools like Gantt charts and Kanban boards help benefit team members in what three ways?

They can translate project contracts like the statement of work (SOW) into number and dollar amounts

They provide clear context about work project details

They can illustrate when they need to complete their individual tasks

They can demonstrate how their individual tasks connect to other tasks in the project

2.

MULTIPLE SELECT QUESTION

45 sec • 1 pt

What are the benefits of Agile projects? Select all that apply.

They embrace the reality that the world, markets, and users are uncertain and unpredictable.

They help the customer realize—and receive—the product they really wanted.

They deliver one product release at the end of the project, which helps save time and energy.

They seek out ways to work more efficiently by streamlining processes without losing value.

3.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

As a project manager selecting a vendor, you first need to outline the details and requirements of your project in order to solicit bids. Which procurement document helps with this task?

A request for proposal (RFP)

A Statement of Work (SOW)

A non-disclosure agreement (NDA)

A work breakdown structure (WBS)

4.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

To create a well-organized budget, a project manager includes different types of expenditures. Which type of budget expense creates a future benefit for a company?

Historical expenses

Capital expenses (CAPEX)

Indirect expenses

Operating expenses (OPEX)

5.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

Fill in the blank: A Scrum Team should be _____, which means people with different skill sets in the organization work together to complete the project successfully.

organized

decisive

self-disciplined

cross-functional

6.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

Associate the project phase to core tasks in a typical project LC: Identify resources

initiating

planning

executing

closing

7.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

Imagine a project manager oversees their company’s transition to a new financial management system. They determine that the project goal is to make the financial portal easier for employees to use. They also identify key stakeholders and outline project objectives. During which phase of the project life cycle do these activities take place?

Close the project

Execute and complete tasks

Initiate the project

Make a plan

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?