19 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

5 mins • 1 pt

Define critical path:

It is that sequence with a greater amount of activities on the time.

It is that sequence with a smaller amount of activities on the time.

It is that sequence with a real activity on the time.

2.

MULTIPLE CHOICE QUESTION

5 mins • 1 pt

Select correct answer: It is a manufacturing control system, is the one that adjusts the flows just in time, using a signaling device.

Kanban

Lean manufacturing

Kaizen

3.

MULTIPLE CHOICE QUESTION

5 mins • 1 pt

Select correct answer: It is a main advantage of using JIT method.

Both answers

Supplier development

Reduction on the levels of inventory

4.

MULTIPLE CHOICE QUESTION

5 mins • 1 pt

A software that has a segment of operations, which can be complex. It has many applications such as the supply and logistics, material administration, plant maintenance, quality administration, among others.

SAP

Microsoft Office

Autocad

5.

MULTIPLE CHOICE QUESTION

5 mins • 1 pt

What is the main objective of the CPM and PERT technique?

Determines the programming of each activity of the project.

Determines the minimum cost of a project

Determines the maximum cost of a project

6.

MULTIPLE CHOICE QUESTION

5 mins • 1 pt

It is responsible for establishing the production rates per similar products groups for a mid-term period (between 3 and 18 months). Its main purpose is to clarify the optimal combination of the production rate, the human resource level, and the inventory in the process.

The planning process

The operations planning process

7.

MULTIPLE CHOICE QUESTION

15 mins • 1 pt

Media Image

McCow Burgers carries out the following activities to serve its customers: Make a PERT diagram and answer, what is the best time of this process? Consider all activities.

8.7 minutes

6 minutes

11.2 minutes

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?