PM1 - 2.01 (FHS - Moffitt)

PM1 - 2.01 (FHS - Moffitt)

12th Grade

11 Qs

quiz-placeholder

Similar activities

ENT Chapter 3 Test Prep Questions

ENT Chapter 3 Test Prep Questions

9th Grade - University

15 Qs

Unit 5 Test Review

Unit 5 Test Review

9th - 12th Grade

14 Qs

Project Based Learning (PBL)

Project Based Learning (PBL)

10th - 12th Grade

10 Qs

File Extension Practice

File Extension Practice

10th - 12th Grade

11 Qs

Principles of Business Revision

Principles of Business Revision

9th Grade - University

10 Qs

Bookkeeping

Bookkeeping

12th Grade

15 Qs

Business Unit 1

Business Unit 1

10th Grade - Professional Development

13 Qs

Accounting Ch3

Accounting Ch3

10th - 12th Grade

11 Qs

PM1 - 2.01 (FHS - Moffitt)

PM1 - 2.01 (FHS - Moffitt)

Assessment

Quiz

Business

12th Grade

Hard

Created by

Penny Moffitt

FREE Resource

11 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

15 mins • 1 pt

An employee has been asked to evaluate a project that is experiencing

some performance challenges. She asked the project manager to call a

meeting with the project sponsor. The project manager replies that he

does not know who the project sponsor is. The employee decides to

review the initial project document. Which document should she request?

business case

project baseline document

project charter

project plan

2.

MULTIPLE CHOICE QUESTION

15 mins • 1 pt

"The magazine will feature 10 items and will be completed over six

months. The cover will be printed in color. The bound pages will be

printed in black and white." This description belongs in the graphic design

project:

business case.

expert judgment.

milestones summary.

statement of work.

3.

MULTIPLE CHOICE QUESTION

15 mins • 1 pt

A team is developing the project charter and is determining the valuable

inputs used for completing the project. The input(s) that the team should

least likely consider when developing the project charter would be the:

business case.

enterprise environmental factors.

project management plan.

project statement of work.

4.

MULTIPLE CHOICE QUESTION

15 mins • 1 pt

Brian would like to purchase his first home. He is unsure of the inputs

needed to help him manage the details of this project. He sets up an

appointment with his Uncle Joe, who has owned many real estate

properties and is very familiar with the process, to discuss his home

buying project. Which tool or technique is Brian using for input into his

home purchase project?

analytical techniques

consumer survey

expert judgment

planning guide

5.

MULTIPLE CHOICE QUESTION

15 mins • 1 pt

John is planning his wedding. He has never been married and seeks input

from his sister, Lauren. Lauren owns her own wedding planning business.

John is using which tool and technique to guide his wedding project?

change control board

customer request

expert judgment

stakeholder support

6.

MULTIPLE CHOICE QUESTION

15 mins • 1 pt

Christian is a project manager and would like to gain an understanding of

the customer's needs, the budget, and the milestones needed to achieve

the project objectives. Which should he review?

business case

project baseline document

project charter

project plan

7.

MULTIPLE CHOICE QUESTION

15 mins • 1 pt

Delores has just been assigned to be a project manager of a team, and

she would like to find out more about a project. She is unsure of who can

authorize the project. What document should Delores consult?

contract

organizational process assets

project charter

project objectives

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?