11 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

15 mins • 1 pt

An employee has been asked to evaluate a project that is experiencing

some performance challenges. She asked the project manager to call a

meeting with the project sponsor. The project manager replies that he

does not know who the project sponsor is. The employee decides to

review the initial project document. Which document should she request?

business case

project baseline document

project charter

project plan

2.

MULTIPLE CHOICE QUESTION

15 mins • 1 pt

"The magazine will feature 10 items and will be completed over six

months. The cover will be printed in color. The bound pages will be

printed in black and white." This description belongs in the graphic design

project:

business case.

expert judgment.

milestones summary.

statement of work.

3.

MULTIPLE CHOICE QUESTION

15 mins • 1 pt

A team is developing the project charter and is determining the valuable

inputs used for completing the project. The input(s) that the team should

least likely consider when developing the project charter would be the:

business case.

enterprise environmental factors.

project management plan.

project statement of work.

4.

MULTIPLE CHOICE QUESTION

15 mins • 1 pt

Brian would like to purchase his first home. He is unsure of the inputs

needed to help him manage the details of this project. He sets up an

appointment with his Uncle Joe, who has owned many real estate

properties and is very familiar with the process, to discuss his home

buying project. Which tool or technique is Brian using for input into his

home purchase project?

analytical techniques

consumer survey

expert judgment

planning guide

5.

MULTIPLE CHOICE QUESTION

15 mins • 1 pt

John is planning his wedding. He has never been married and seeks input

from his sister, Lauren. Lauren owns her own wedding planning business.

John is using which tool and technique to guide his wedding project?

change control board

customer request

expert judgment

stakeholder support

6.

MULTIPLE CHOICE QUESTION

15 mins • 1 pt

Christian is a project manager and would like to gain an understanding of

the customer's needs, the budget, and the milestones needed to achieve

the project objectives. Which should he review?

business case

project baseline document

project charter

project plan

7.

MULTIPLE CHOICE QUESTION

15 mins • 1 pt

Delores has just been assigned to be a project manager of a team, and

she would like to find out more about a project. She is unsure of who can

authorize the project. What document should Delores consult?

contract

organizational process assets

project charter

project objectives

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?