1.
MULTIPLE CHOICE QUESTION
15 mins • 1 pt
An employee has been asked to evaluate a project that is experiencing
some performance challenges. She asked the project manager to call a
meeting with the project sponsor. The project manager replies that he
does not know who the project sponsor is. The employee decides to
review the initial project document. Which document should she request?
business case
project baseline document
project charter
project plan
2.
MULTIPLE CHOICE QUESTION
15 mins • 1 pt
"The magazine will feature 10 items and will be completed over six
months. The cover will be printed in color. The bound pages will be
printed in black and white." This description belongs in the graphic design
project:
business case.
expert judgment.
milestones summary.
statement of work.
3.
MULTIPLE CHOICE QUESTION
15 mins • 1 pt
A team is developing the project charter and is determining the valuable
inputs used for completing the project. The input(s) that the team should
least likely consider when developing the project charter would be the:
business case.
enterprise environmental factors.
project management plan.
project statement of work.
4.
MULTIPLE CHOICE QUESTION
15 mins • 1 pt
Brian would like to purchase his first home. He is unsure of the inputs
needed to help him manage the details of this project. He sets up an
appointment with his Uncle Joe, who has owned many real estate
properties and is very familiar with the process, to discuss his home
buying project. Which tool or technique is Brian using for input into his
home purchase project?
analytical techniques
consumer survey
expert judgment
planning guide
5.
MULTIPLE CHOICE QUESTION
15 mins • 1 pt
John is planning his wedding. He has never been married and seeks input
from his sister, Lauren. Lauren owns her own wedding planning business.
John is using which tool and technique to guide his wedding project?
change control board
customer request
expert judgment
stakeholder support
6.
MULTIPLE CHOICE QUESTION
15 mins • 1 pt
Christian is a project manager and would like to gain an understanding of
the customer's needs, the budget, and the milestones needed to achieve
the project objectives. Which should he review?
business case
project baseline document
project charter
project plan
7.
MULTIPLE CHOICE QUESTION
15 mins • 1 pt
Delores has just been assigned to be a project manager of a team, and
she would like to find out more about a project. She is unsure of who can
authorize the project. What document should Delores consult?
contract
organizational process assets
project charter
project objectives
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?