1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What does it mean if an “R” is next to your name in a RACI chart?

You are accountable for the result.

You should be engaged to provide required inputs.

You should be kept up to date on the status.

You are responsible for the activity’s execution.

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which is a good practice for the use of collaboration technology?

elect tools with the best features.

Select tools that the team lead has experience using.

Define team goals and practices before selecting tools.

Use the tools that the previous project used.

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following is not a stakeholder in a financial project?

Someone opposed to the project

Project manager

Someone who is not interested in the project

Project sponsor

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following is an artifact that outlines how the team will operate and work together?

Team charter

Resource management plan

Project charter

Team acquisition plan

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which statement best describes project stakeholders?

Anyone affected by the project, its outputs, and its operation

Anyone making money from the project

A customer paying for the project’s output

The organization delivering the project’s products

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following would be least likely to be included in a stakeholder engagement plan?

List of identified project stakeholders

Documentation of the relationships between project stakeholders

Amount of money invested by the project stakeholders

Actions to be used interacting with project stakeholders

7.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

Your company has entered into a contract to develop a new and improved website for another company. The contract specifies the major deliverables, with details about what the website will contain, the completion date, and budget. The appendix contains the change control procedures that will be used. What project life cycle should be used to deliver this project?

Predictive

Agile

Hybrid

Scrum

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?