Software Engineering - cocomo model and risk management

Software Engineering - cocomo model and risk management

University

10 Qs

quiz-placeholder

Similar activities

Website Usability and UX

Website Usability and UX

University

10 Qs

DAWN CIE

DAWN CIE

University

15 Qs

Information Security Principles

Information Security Principles

University

10 Qs

Topic 4 System Software

Topic 4 System Software

University

10 Qs

Java Quiz 4

Java Quiz 4

University

15 Qs

HCI Week 3

HCI Week 3

University

10 Qs

CBA Excel 1

CBA Excel 1

University

10 Qs

Quiz - CSE

Quiz - CSE

University

10 Qs

Software Engineering - cocomo model and risk management

Software Engineering - cocomo model and risk management

Assessment

Quiz

Computers

University

Medium

Created by

Kowsalya P

Used 4+ times

FREE Resource

10 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

COCOMO stands for ------------

Constructive Cost Model

Comprehensive cost model

Constructive cost estimation model

Complete cost estimation model

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which version of cocomo states that once requirements have been stabilized, the basic software architecture has been established?

Early- design stage model

Post-architecture stage model

Application composition model

All of the mentioned

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

COCOMO was developed initially by ----------

B.Beizar

B.W.Bohem

Rajiv Gupta

Gregg Rathermal

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which one is not a risk management activity?

Risk assessment

Risk generation

Risk control

None of the mentioned

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which model was used during the early stages of software engineering, when prototyping of user interfaces , consideration of software and system interaction, assessment of performance, and evaluation of technology maturity were paramount?

Early design stage model

Post architecture stage model

Application composition model

All of the mentioned

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Risk management is one of the most important jobs for a ---------

Client

Investor

Production team

Project manager

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following risk is the failure of a purchased component to perform as expected?

Product risk

Project risk

Business risk

Programming risk

Create a free account and access millions of resources

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

By signing up, you agree to our Terms of Service & Privacy Policy

Already have an account?