A client has requested a major feature addition that will add significant development time to the project. What is the best course of action?
Digital Project Manager Role

Quiz
•
Computers
•
University
•
Hard
Sadia Riaz
FREE Resource
10 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
a) Agree to the client's request and extend the project timeline
b) Decline the client's request and stick to the original timeline
c) Propose an alternate solution that would address the client's needs within the original timeline
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
During the design phase of a project, a stakeholder suggests a major change to the project scope. What is the best course of action?
a) Implement the stakeholder's suggestion
b) Stick to the original project scope
c) Discuss the impact of the stakeholder's suggestion on the project timeline and budget
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A team member is consistently missing deadlines and not communicating their progress. What is the best course of action?
a) Confront the team member and demand an explanation
b) Schedule a one-on-one meeting with the team member to discuss their workload and any obstacles they may be facing
c) Ignore the team member's behavior and hope it improves
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A client requests a feature that is outside the project scope and would significantly delay the project timeline. What is the best course of action?
a) Suggest that the feature be added to a future phase of the project
b) Decline the client's request and stick to the original timeline
c) Agree to the client's request and extend the project timeline
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
During the testing phase of a project, a critical bug is discovered that could significantly delay the project timeline. What is the best course of action?
a) Ignore the bug and hope it doesn't cause any major issues
b) Prioritize fixing the bug and communicate the impact on the project timeline to the client
c) Inform the client of the issue and request an extension to the project timeline
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A team member requests time off during a critical phase of the project. What is the best course of action?
a) Deny the team member's request and require them to work during the critical phase
b) Allow the team member to take time off and adjust the project timeline accordingly
c) Discuss the impact of the team member's absence on the project timeline and workload, and come up with a solution that works for everyone
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
The design team has created a new user interface that has not been user tested. The development team is requesting to start integrating it into the code. What should the digital project manager do?
a) Grant permission for integration
b) Request user testing before integration
c) Ask for an explanation from the design team
d) Ask for an explanation from the development team
Create a free account and access millions of resources
Similar Resources on Quizizz
15 questions
Computing 1 Chapter 4

Quiz
•
University
15 questions
First Quiz - CS326C

Quiz
•
University
15 questions
Data Model Using Spreadsheet

Quiz
•
12th Grade - University
10 questions
Managing Digital Projects

Quiz
•
University
12 questions
Lesson 1 - The Basics

Quiz
•
University
12 questions
R081 Pre-production documents

Quiz
•
11th Grade - Professi...
15 questions
Introduction of Flash

Quiz
•
12th Grade - University
14 questions
Week 11: Review

Quiz
•
University
Popular Resources on Quizizz
15 questions
Multiplication Facts

Quiz
•
4th Grade
20 questions
Math Review - Grade 6

Quiz
•
6th Grade
20 questions
math review

Quiz
•
4th Grade
5 questions
capitalization in sentences

Quiz
•
5th - 8th Grade
10 questions
Juneteenth History and Significance

Interactive video
•
5th - 8th Grade
15 questions
Adding and Subtracting Fractions

Quiz
•
5th Grade
10 questions
R2H Day One Internship Expectation Review Guidelines

Quiz
•
Professional Development
12 questions
Dividing Fractions

Quiz
•
6th Grade