RMP - 6. MONITOR & CLOSE RISK

RMP - 6. MONITOR & CLOSE RISK

1st Grade

14 Qs

quiz-placeholder

Similar activities

RMP - 2. STRATEGY & PLANNING

RMP - 2. STRATEGY & PLANNING

1st Grade

16 Qs

RMP - 1. INTRODUCTION

RMP - 1. INTRODUCTION

1st Grade

13 Qs

PMI SH Manage Project Issues

PMI SH Manage Project Issues

1st Grade

12 Qs

IT QUIZ

IT QUIZ

1st - 12th Grade

15 Qs

Multiple Choice

Multiple Choice

1st - 2nd Grade

14 Qs

PMI SH - Plan and Manage Procurement

PMI SH - Plan and Manage Procurement

1st Grade

18 Qs

PMI SH - Integrate Project Planning Activities

PMI SH - Integrate Project Planning Activities

1st Grade

18 Qs

08. Quality Management

08. Quality Management

1st - 3rd Grade

12 Qs

RMP - 6. MONITOR & CLOSE RISK

RMP - 6. MONITOR & CLOSE RISK

Assessment

Quiz

Professional Development

1st Grade

Medium

Created by

sudiyuwono wowo

Used 4+ times

FREE Resource

14 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

During a risk audit, it was found that some risks were not analyzed correctly. It was suspected that risk-related information was not properly reviewed before concluding characteristics of risks like probability, etc. What could have been done to prevent this issue?
Effective interviews during the risk identification process.
Risk probability and impact assessment.
Risk data quality assessment.
Analysis of other parameters.

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The project risk manager for an environmental preservation project has started the process of monitoring and controlling risks. The project manager has asked the project team to document the results of this process. How should this documentation be utilized in the future?
To comply with the rules and regulations.
To ensure information is recorded for lessons learned.
To hold those whose created the risk accountable.
To return the remaining amount of the contingency reserve.

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

You are the project manager for your organization. You have determined that an activity is too dangerous to complete internally so you hire a licensed contractor to complete the work. The contractor, however, may not complete the assigned work on time which could cause delays in subsequent work beginning. This is an example what type of risk event?
Secondary risk.
Transference.
Trigger conditions.
Fallback plans.

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Based on this analysis, which two risk areas should the project manager focus on to control project cost?
Raw Materials cost and cost of install equipment.
Cost of control room and cost of install equipment.
Raw materials cost and labor rate increases.
Cost of temporary facilities and design changes.

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

When should project risks be closed?
When the risk has been realized and can no longer happen again.
When the forecast activity date has been met or exceeded.
When iterative data analysis determines the risk is not applicable.
When the stakeholders agree a risk is no longer applicable.

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Stakeholder deliverable reviews will start soon and additional work is expected to resolve any issues or required adjustment. Budget overruns during execution have put serious constraints on the remainder of the project's budget. What should the project manager do next?
Coach stakeholders on risk identification practices.
Review the consequences of potential changes.
Conduct a risk reassessment and reserve analysis.
Request a budget relief using the management reserve.

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The risk register is developed during the initial phases of a virtualized desktop deployment. The register is reviewed by peers, responses are planned, reviewed again, and risks are prioritized. After project completion the risk register is reviewed as a part of the formal lessons learned process. During the review, it's realized that the risk register wasn't updated, and many responses were not executed during the deployment. Which of the following options should have been performed during the execution of the project?
Risk management process.
Risk monitoring and control process.
Response planning.
Risk identification.

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?