
4.00 Project Management Reveiw
Authored by Cheree Breeden
Business
9th - 12th Grade
Used 8+ times

AI Actions
Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...
Content View
Student View
24 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec โข 1 pt
Craig needs to weld the car chassis together before Jim can install the engine. This represents a/an:
abstract dependency
discretionary dependency
external dependency
mandatory dependency
2.
MULTIPLE CHOICE QUESTION
30 sec โข 1 pt
The project manager and team have created the schedule for the hospital wireless network upgrade project. The schedule includes a five-day delay for the network approval before the hospital can use the upgraded network. This causes the finish date of the project to slip by five days. This hospital network project is:
accelerating
forming
lagging
leading
3.
MULTIPLE CHOICE QUESTION
30 sec โข 1 pt
Which process puts more resources on the critical path?
crashing
fast tracking
leading
shortening
4.
MULTIPLE CHOICE QUESTION
30 sec โข 1 pt
Which process puts more resources on the critical path?
1. Activity e with preceding activities STart, and duration of 8 days
2. Activity F with preceding activities E and duration of 4 days
3. Activity G with preceding activities E and duration of 10 days
4. Activity H with preceding activities F and G and duration of 2 days
5. Activity I with preceding activities H and duration of 2 days
6. Activity J with preceding activities H and duration of 2 days
7. Activity K with preceding activities H and duration of 3 daus
8. Activity L with preceding activities I, J, and K and duration of 2 days
9. Activity M with preceding activities L and duration of 1 day
19 days
25 days
26 days
27 days
5.
MULTIPLE CHOICE QUESTION
30 sec โข 1 pt
Which process requires the project manager to analyze the network diagram and sequencing to see whether any activities can be done in parallel on the critical path?
crashing
fast tracking
leading
shortening
6.
MULTIPLE CHOICE QUESTION
30 sec โข 1 pt
In order to complete the finished attic remodel project on time, Brian decides to hang the ceiling fan while Petrina paints the walls. This is an example of schedule:
crashing
fast tracking
leading
shortening
7.
MULTIPLE CHOICE QUESTION
30 sec โข 1 pt
It took Scott's team two hours to mow and edge one acre of land. He estimates that it will take his team eight hours to mow and edge four acres of land for an upcoming project. Scott's duration estimation for this project is an example of:
bottom up estimating
parametric estimating
reserve analysis
three point estimating
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?