Part 3 - DSN new

Part 3 - DSN new

University

10 Qs

quiz-placeholder

Similar activities

SMAK

SMAK

University

6 Qs

Gestão de Projetos - 1. Início

Gestão de Projetos - 1. Início

University

9 Qs

IOR quiz

IOR quiz

University - Professional Development

10 Qs

Project Management

Project Management

University

10 Qs

Develop schedule

Develop schedule

University

7 Qs

Planificación Operativa

Planificación Operativa

University

8 Qs

REPRESENTACIÓN DE PROYECTOS MEDIANTE UNA RED

REPRESENTACIÓN DE PROYECTOS MEDIANTE UNA RED

University

10 Qs

Análisis de redes

Análisis de redes

University

9 Qs

Part 3 - DSN new

Part 3 - DSN new

Assessment

Quiz

Professional Development

University

Medium

Created by

Kavitha GRGSMS

Used 19+ times

FREE Resource

10 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

This is the shortest possible time in which the activity can be finished. It assumes that everything goes well.

Optimistic

Pessimistic

Most Likely

Accurate

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

  • The longest possible time required to perform an activity under extremely bad conditions

Optimistic

Pessimistic

Most Likely

Accurate

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Critical path is the

shortest time path in a network 

longest time path in a network 

efficient time path in a network 

optimal time path in a network 

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Activities with zero slack lie on a

Non-Critical path

Critical path

Normal path

Crash path

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A ______ is a graphical representation of arrows and nodes for showing logical sequence of activities performed to achieve a project objectives.

Bar

Network

Chart

Diagram

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

If duration of each activity in a project scheduling is not known with certainty then ____ network model is used

CPM

PERT

PEST

Deterministic

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

________ analysis is used for planning, scheduling and controlling large complex projects.

Transportation

LPP

Network

Assignment

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?