Pressure testing cold water pipework

Pressure testing cold water pipework

1st - 10th Grade

7 Qs

quiz-placeholder

Similar activities

CDA - Who wants to be a Millionaire? Part 2

CDA - Who wants to be a Millionaire? Part 2

1st Grade

10 Qs

Syllabus Quiz

Syllabus Quiz

10th Grade

12 Qs

WildChina Education Freelancer FAQs

WildChina Education Freelancer FAQs

KG - University

11 Qs

Testing Irregularities

Testing Irregularities

KG - 12th Grade

5 Qs

09/26/2017 Intro to Engineering Design period #7

09/26/2017 Intro to Engineering Design period #7

9th - 12th Grade

10 Qs

Growth Mindset Review

Growth Mindset Review

7th - 8th Grade

10 Qs

Review of procedures for A2 KEY

Review of procedures for A2 KEY

4th - 7th Grade

10 Qs

Beginning of School (Adjective Review)

Beginning of School (Adjective Review)

KG - University

10 Qs

Pressure testing cold water pipework

Pressure testing cold water pipework

Assessment

Quiz

Professional Development

1st - 10th Grade

Medium

Created by

Luke Rock

Used 5+ times

FREE Resource

7 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 3 pts

All water fittings should be capable of withstanding an internal water pressure of not less than................ times the maximum operating pressure.

1.2

1.5

1.7

2

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

When testing rigid pipe systems all the outlets should be sealed and all float operated valves should be capped off or isolated.

The water pressure should then be increased, by pumping, until the lowest point in the installation is 50% above the normal operating pressure. This pressure should be maintained for..................... without further pumping.

30mins

1hour

1.5hours

2hours

3.

MULTIPLE SELECT QUESTION

45 sec • 1 pt

Which of the following problems should be rectified before testing?

Insufficient clips

Lagging pipes

incorrectly installed service valves

Make sure you have open ends

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Once a hydraulic test bucket has been used to pump up the pressure to the correct test pressure, how long should it be left for?

30mins

1hour

1.5hours

45mins

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

How many tests are there for systems containing plastic pipe?

1, test A

2, Test A and test B

3, Test A, B & C

1, same as the rigid pipe test

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Test A is passed if the pressure does not drop below one-third of the test pressure over the following............... minutes and there is no visible leakage throughout the test.

60mins

90mins

120mins

45mins

7.

MULTIPLE SELECT QUESTION

45 sec • 1 pt

The customer should be issued with which of the following documents during the handover:

The bill

Manufacturer's instructions

Warranty

Benchmark