Quality Control Measures in Asphalt Pavement Construction

Quality Control Measures in Asphalt Pavement Construction

Professional Development

10 Qs

quiz-placeholder

Similar activities

Medio ambiente

Medio ambiente

Professional Development

8 Qs

Cyber Security Awareness

Cyber Security Awareness

Professional Development

10 Qs

First Impressions - Professional and Personal

First Impressions - Professional and Personal

Professional Development

7 Qs

Haier ACs Quiz

Haier ACs Quiz

Professional Development

10 Qs

Plant Tech 2021 .2

Plant Tech 2021 .2

Professional Development

11 Qs

Logos

Logos

1st Grade - Professional Development

10 Qs

National Wool Week 2019

National Wool Week 2019

Professional Development

8 Qs

Environmental changes

Environmental changes

Professional Development

15 Qs

Quality Control Measures in Asphalt Pavement Construction

Quality Control Measures in Asphalt Pavement Construction

Assessment

Quiz

Instructional Technology, Other, Professional Development

Professional Development

Medium

Created by

Neilsen Campit

Used 3+ times

FREE Resource

10 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

Media Image

Constant checking of bituminous mixture as it leaves the pugmill/central mixing plant for compliance with the job-mix formula is important. Hence, the tolerance temperature of asphalt mix is:

165 degree Celsius

110 degree Celsius

130 degree Celsius

120 degree Celsius

2.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

Media Image

It is an assembly of mechanical and electronic equipment where aggregates, recycled materials, or other additives are blended, heated, dried, and mixed with a binder to produce an asphalt mixture meeting specified requirements.

Asphalt Batch-Type Mixing Plant

Asphalt Mixture Plant

Asphalt Drum-Type Mixing Plant

Portland Cement Concrete Mixture Plant

3.

MULTIPLE SELECT QUESTION

20 sec • 1 pt

Media Image

Quality asphalt pavement has:

Good design

Good quality of materials

Good construction control or workmanship

Good foundation

Good drainage

4.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

Media Image

What is the required stability (index retain strength) of the asphalt mix when tested by AASHTO T165?

greater than or equal to 70

less than or equal to 70

greater than 70

less than 70

5.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

Media Image

What are the basis of acceptance and final payment on the completed asphalt pavement?

thickness and strength determination

thickness and density determination

thickness determination only

density determination only

6.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

Media Image

The variation of the surface from the testing edge (3-m straight edge) between contact with the surface shall ________.

exceed 6 millimeters

not exceed 6 millimeters

not exceed 8 millimeters

exceed 8 millimeters

7.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

Media Image

The mixture shall be placed at a temperature ____________ as measured in the truck prior to dumping into the spreader.

not less than 107 degree Celsius

less than 107 degree Celsius

not less than 105 degree Celsius

less than 105 degree Celsius

Create a free account and access millions of resources

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

By signing up, you agree to our Terms of Service & Privacy Policy

Already have an account?