Scope Management - Campus Biomedico

Scope Management - Campus Biomedico

Professional Development

5 Qs

quiz-placeholder

Similar activities

Scope Management Process - Assignment

Scope Management Process - Assignment

Professional Development

7 Qs

SG20_Test_S4_CH5 Scope

SG20_Test_S4_CH5 Scope

Professional Development

10 Qs

Project Management

Project Management

Professional Development

10 Qs

Understand Project Scope Management

Understand Project Scope Management

Professional Development

7 Qs

IPMAC_PMP_L08P_Scope Management

IPMAC_PMP_L08P_Scope Management

Professional Development

10 Qs

Project Integration Management Quiz

Project Integration Management Quiz

Professional Development

10 Qs

PMP PROJECT COMMUNICATIONS MANAGEMENT

PMP PROJECT COMMUNICATIONS MANAGEMENT

Professional Development

10 Qs

Project Scope Management

Project Scope Management

Professional Development

10 Qs

Scope Management - Campus Biomedico

Scope Management - Campus Biomedico

Assessment

Quiz

Professional Development

Professional Development

Hard

Created by

Michelle Caicedo

Used 1+ times

FREE Resource

5 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

The scope baseline is an output of which process?

plan scope management

collect requirements

define scope

create WBS

2.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

Which document  is used to identify the people who can provide information and detailed requirements:

The requirements documentation

The stakeholder register

The work breakdown structure

The project charter

3.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

The WBS should be decomposed to as detailed as:

possible based on the scope of the work

money allows in the project budget

time allows in the project schedule

the ability to plan, manage, and control the work is enhanced

4.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

Verified deliverables are:

an input to validate scope

an input of control quality

an input to direct and manage project work

an output of validate scope

5.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

The change requests that are an output of validate scope become an input of which process?

Develop project management plan

Monitor and control project work

Perform integrated change control

Close project or phase