Chapt3

Chapt3

1st Grade

10 Qs

quiz-placeholder

Similar activities

01. Introduction PMP  and Agile

01. Introduction PMP and Agile

1st Grade

12 Qs

Agile Exam Preparation

Agile Exam Preparation

1st Grade

10 Qs

08. Quality Management

08. Quality Management

1st - 3rd Grade

12 Qs

Communication Management

Communication Management

1st - 3rd Grade

10 Qs

Chapt 6

Chapt 6

1st Grade

10 Qs

PMI-SH Assess and Manage Risks

PMI-SH Assess and Manage Risks

1st Grade

11 Qs

PMI-ACP (10D)

PMI-ACP (10D)

1st Grade

10 Qs

06. Schedule Management

06. Schedule Management

1st - 3rd Grade

12 Qs

Chapt3

Chapt3

Assessment

Quiz

Professional Development

1st Grade

Medium

Created by

WS Ho

Used 4+ times

FREE Resource

10 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

45 sec • 5 pts

The need for __ is one of the major driving forces for communication in a project.

A. Optimization

B. Integrity

C. Integration

D. Differentiation

2.

MULTIPLE CHOICE QUESTION

45 sec • 5 pts

The customer has accepted the completed project scope. However, the lessons learned required by the project management office have not been completed. What is the status of the project?

A. The project is incomplete because it needs to be replanned

B. The project is incomplete until all project and product deliverables are complete and accepted

C. The project is complete because the customer has accepted the deliverables.

D. The project is complete because it has reached its due date.

3.

MULTIPLE CHOICE QUESTION

45 sec • 5 pts

A project is plagued by changes to the project charter. Who has the primary responsibility to decide if these changes are necessary?

A. The project manager

B. The project team

C. The sponsor

D. The stakeholders

4.

MULTIPLE CHOICE QUESTION

45 sec • 5 pts

Effective project integration usually requires an emphasis on:

A. The personal careers of the team members

B. Timely updates to the project management plan

C. Effective communication at key interface points

D. Product control

5.

MULTIPLE CHOICE QUESTION

45 sec • 5 pts

Integration is managed by the:

A. Project manager

B. Team

C. Sponsor

D. Stakeholders

6.

MULTIPLE CHOICE QUESTION

45 sec • 5 pts

Which of the following BEST describes the project manager's role as an integrator?

A. Help team members become familiar with the project

B. Put all the pieces of a project into a cohesive whole

C. Put all the pieces of a project into a program

D. Get all team members together into a cohesive whole

7.

MULTIPLE CHOICE QUESTION

45 sec • 5 pts

Which of the following BEST describes a project management plan?

A. A printout from project management software

B. A detail project schedule

C. Risk, human resource, process improvement, and other management plans

D. The project scope

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?