A Project Sponsor appointed a Project Manager to a new project and asked her
to get started immediately - even before the charter got approved. What should the
Project Manager do?
IT PROJECT MANAGEMENT
Quiz
•
Business
•
University - Professional Development
•
Medium
Collins Ampofo
Used 20+ times
FREE Resource
40 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A Project Sponsor appointed a Project Manager to a new project and asked her
to get started immediately - even before the charter got approved. What should the
Project Manager do?
Ask some project manager to take over
Start critical activities
Push to create and approve the chatter
Start with team up and planning
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which of the following is not required at the requirements elicitation and
analysis stage of an IT project management lifecycle?
Interviewing users and their managers
Examining documentation describing the current operations.
Incentivising key stakeholders
Analysing operational records created by the current system.
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is referred to as the application of knowledge, skills, tools, and
techniques to project activities to meet an IT project requirement?
Requirement elicitation
Scope management
Schedule Management
IT Project Management
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Where a new application is to be built, the elements to be designed include all
except
Input
Process
Requirement statement
Output
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What most important purpose does a project chatter serve for the IT-Pmiect
Manager?
Describes the cost of the project
Describes the project float
Describes the project scope
Describe the project Process Design
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In identifying a business case for an IT project, what can be refer to as
feasibility report which, among other things, presents the business with a range of
options aimed at providing a solution?
Project Statement of Work
Deliverable
Milestone Chart
Project Charter
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In identifying a business case for an IT Project, What is referred to as the
analysis of the benefits vis-a-vis the estimated costs and the. ability of the
organisation to have the resources to pay for the investment?
Technical Constraint Analysis
Time Constraint Analysis
Organisational Constraint Analysis
Budget Constraint
42 questions
FINAL TEST MGT300 INFORMATION TECHNOLOGY IN BUSINESS
Quiz
•
University
36 questions
Economics Quiz
Quiz
•
University
40 questions
Assessment 2: Basic Considerations in MAS
Quiz
•
University
36 questions
Technical Test
Quiz
•
Professional Development
40 questions
IBT_Midterms (INCOMPLETE)
Quiz
•
University
40 questions
Hospitality and Tourism Business (ASEAN)
Quiz
•
University
38 questions
Marketing II Prep
Quiz
•
11th Grade - University
40 questions
Parcial 1- Org Theory
Quiz
•
University
15 questions
Multiplication Facts
Quiz
•
4th Grade
20 questions
Math Review - Grade 6
Quiz
•
6th Grade
20 questions
math review
Quiz
•
4th Grade
5 questions
capitalization in sentences
Quiz
•
5th - 8th Grade
10 questions
Juneteenth History and Significance
Interactive video
•
5th - 8th Grade
15 questions
Adding and Subtracting Fractions
Quiz
•
5th Grade
10 questions
R2H Day One Internship Expectation Review Guidelines
Quiz
•
Professional Development
12 questions
Dividing Fractions
Quiz
•
6th Grade