Managing Project Scheduling

Managing Project Scheduling

University

20 Qs

quiz-placeholder

Similar activities

Project Management_Execution

Project Management_Execution

University

15 Qs

FInance Management

FInance Management

University

18 Qs

Project Management_Planning (2)

Project Management_Planning (2)

University

21 Qs

Midterm Exam in Introduction to Project Management

Midterm Exam in Introduction to Project Management

University

15 Qs

Project Management - Midterm Exam

Project Management - Midterm Exam

University

20 Qs

Flash Card Quiz: Network Analysis Quiz

Flash Card Quiz: Network Analysis Quiz

12th Grade - University

23 Qs

PM - Chapter 5

PM - Chapter 5

University

18 Qs

Project Management Quiz - Scope, Quality and Risk

Project Management Quiz - Scope, Quality and Risk

University

18 Qs

Managing Project Scheduling

Managing Project Scheduling

Assessment

Quiz

Business

University

Hard

Created by

Katrina Geluz

Used 11+ times

FREE Resource

20 questions

Show all answers

1.

FILL IN THE BLANK QUESTION

1 min • 1 pt

___________________ simply defined, involves the processes required to ensure timely completion of a project.

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

____________ grow out of the basic documents that initiate a project.

Sequence Activities

Plan Schedule Management

Define Activities

Estimate Activity Durations

Develop Schedule

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

______________ is a tabulation of activities to be included in a project schedule.

Sequence Activities

activity attributes

activity list

Define Activities

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A dependency or relationship pertains to the scheduling of project activities or tasks.

TRUE

FALSE

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

_______________ involve relationships between project activities that are generally inside the project team's control.

Mandatory dependencies

Discretionary dependencies

External dependencies

Internal dependencies

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

It is the process of estimating the number of work periods needed to complete individual activities with estimated resources.

Plan Schedule Management

Control Schedule

Estimate Activity Durations

Develop Schedule

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

It is the process of monitoring the status of the project to update the project schedule and managing changes to the schedule baseline.

Estimate Activity Durations

Develop Schedule

Control Schedule

Define Activities

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?