Agile

Agile

Professional Development

24 Qs

quiz-placeholder

Similar activities

Human and Computer Interaction

Human and Computer Interaction

University - Professional Development

23 Qs

XDXDXD

XDXDXD

Professional Development

20 Qs

[BIA - TIARA] Chapter 5

[BIA - TIARA] Chapter 5

Professional Development

20 Qs

Project Management - SEA-TVET

Project Management - SEA-TVET

Professional Development

20 Qs

敏捷Scrum基础

敏捷Scrum基础

Professional Development

20 Qs

Repaso de lo aprendido hasta ahora

Repaso de lo aprendido hasta ahora

Professional Development

20 Qs

Scrum Roles Quiz

Scrum Roles Quiz

Professional Development

20 Qs

SCRUM Debriefing Test

SCRUM Debriefing Test

Professional Development

26 Qs

Agile

Agile

Assessment

Quiz

Computers

Professional Development

Easy

Created by

ThaoTP Tran

Used 4+ times

FREE Resource

24 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

1. Tracking project impediments in a Scrum project is whose primary responsibility? 
A. Tester 
B. Scrum Master 
C. Functional Manager 
D. Developer 

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

2. Which concept of the following is Not defined in the Scrum Framework? 
A. ScrumMaster 
B. Project Manager 
C. Scrum Product Owner 
D. Daily Scrum 

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

3. Which of the following main events are defined by Scrum Framework?<br />i. Sprint Planning Meeting<br />ii. Sprint Retrospective Meeting<br />iii. Sprint Review Meeting<br />iv. Mid-Sprint Status Review Meeting<br />v. Daily Scrum Meeting<br />
A.      i, ii, iii, iv, v
B.      i, ii, iii, iv
C.      i, ii, iii, v
D.      I, iii, iv, v

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Who is responsible for prioritizing the product backlog?
A.      Product Owner
B.      Project Manager
C.       Lead Developer
D.      Business Analyst

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What does NOT belong to the agile manifesto’s main pillars?
A.      Individuals and interactions over processes and tools
B.      Working software over comprehensive documentation
C.      Processes over people
D. Customer collaboration over contract negotiation

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following is NOT a typical artifact of the Scrum framework?
A.      Product Backlog
B.      Sprint Backlog
C.       Burn down chart
D.      Gantt chart

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

How should work be allocated to the team in an agile project?
A.      The Team Leader (SM) should allocate specific tasks to individuals
B.      Task should be randomly allocated to team members, using Planning Poker
C.      Team members should self-select tasks appropriate to their skills
D.      The most complex tasks should be allocated by the Team Leader (SM)

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?