FMT203_Procurement and Contract Management_SU5

FMT203_Procurement and Contract Management_SU5

University

10 Qs

quiz-placeholder

Similar activities

Lathe and Lathe work - Lesson 02

Lathe and Lathe work - Lesson 02

University

10 Qs

Occupational Therapy

Occupational Therapy

University

15 Qs

Educational Leadership: Culture and Diversity CH1

Educational Leadership: Culture and Diversity CH1

University

10 Qs

INTO Artificial Intelligence

INTO Artificial Intelligence

University - Professional Development

10 Qs

Quan hệ lao động

Quan hệ lao động

University

10 Qs

CLB SAFC

CLB SAFC

University

13 Qs

Radio Interface

Radio Interface

University

15 Qs

P2TL SESI-3

P2TL SESI-3

University

10 Qs

FMT203_Procurement and Contract Management_SU5

FMT203_Procurement and Contract Management_SU5

Assessment

Quiz

Professional Development

University

Hard

Created by

Alphonsus Ee

Used 6+ times

FREE Resource

10 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

Media Image

Which of the following does NOT amount to a variation?

An oder to work overtime/ increase manpower due to an emergency at the site.

An order to increase the wage of cleaners progressively due to a change in regulation.

An order to implement safe management measures due to new regulations.

An order to deduct a significant portion of the contract work and award it to another contractor.

2.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

Media Image

All variation orders given by the contract administrator will result in addtional payment to the service provider.

True

False

3.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

Media Image

The schedule of rates should be used as the first recourse when valuing variations.

True

False

4.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

Under the SIA form of contract, the architect must issue a/an ______ to secure compliance from the service provider.

instruction

variation order

direction

purchase order

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In the PSSCOC form of contract, there is no provision for direction.

True

False

6.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

Which of the following is Not covered under the SOP Act?

HDB renovation projects for HDB flats.

Consultancy contracts for building construction.

Construction contracts that are registered with BCA.

Supply contracts for construction works.

7.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

Which of the following statements about the SOP Act is FALSE?

A contactor is allowed to claim once a month.

A contactor who submits an early payment claim is not entitled to an early payment.

Payment claims can be made after 30 months from the date of delivery.

A payment must be paid when there is a payment claim.

Create a free account and access millions of resources

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

By signing up, you agree to our Terms of Service & Privacy Policy

Already have an account?