A community healthcare centre with hospital emergency departments falls under MLO Lighting Zone 2. The project has associated helipad as well. The road leading to the health centre has government mandated roadway lighting. What exterior lighting would be exempt from SS Credit Light Pollution Reduction?
Sustainable Sites | BD+C

Quiz
•
Architecture
•
Professional Development
•
Hard
Tony Vannoy
Used 1+ times
FREE Resource
83 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
Hospital emergency department, helipad, roadway lighting
Parking lot, roadway lighting, and walking paths
Roadway, national flag, and roadway lighting
Walking paths, landscape lighting, and parking lot
Answer explanation
The following exterior lighting is exempt from the requirements, provided it is controlled separately from the non exempt lighting:
•• Specialized signal, directional, and marker lighting for transportation•• Lighting that is used solely for façade and landscape lighting in MLO lighting zones 3 and 4, and is automatically turned off from midnight until 6 a.m.•• Lighting for theatrical purposes for stage, film, and video performances•• Government mandated roadway lighting•• Hospital emergency departments, including associated helipads•• Lighting for the national flag in MLO lighting zones 2, 3, or 4•• Internally illuminated signage
2.
MULTIPLE SELECT QUESTION
1 min • 1 pt
A BD+C New Construction Project is pursuing SS Credit Heat Island Reduction – Option 2. Parking Under Cover. The project decides to place a minimum of 75% of parking spaces under cover. Which among the following measures will assist the project to earn the credit under Option 2? (Choose 4)
Roof used to shade or cover parking must be covered by energy generation systems, such assolar thermal collectors, photovoltaics, and wind turbines.
Provide parking underground, under deck, under roof, or under building
Roof used to shade or cover parking must be a vegetated roof
Roof used to shade or cover parking must have a three year aged SRI of at least 29 or initla SRI of 32
Roof used to shade or cover parking must have a three year aged SRI of at least 32 or initla SRI of 39
Answer explanation
The choice related to SRI roofing material is not compliant as low sloped roofing materials should have an initial SRI of 82 or higher.
All other choices are correct except “Place a minimum of 75% of parking spaces under cover”. This applies to option 2 – “Option 2. Parking under Cover”.
3.
MULTIPLE SELECT QUESTION
1 min • 1 pt
A BD+C New Construction project is pursuing SS credit Heat Island Reduction – Option 1 – Roof and Non-roof. Which among the following variables must the project consider for the calculation? (Choose 4)
Area of High-Reflectance Roof
Roof area covered by mechanical equipment
Area of Non-roof Measures
Total Roof Area
Area of Vegetated Roof
Answer explanation
Please refer the standard non-roof or roof calculation formula.
Total site area is misleading. Though you need to exclude roof area covered by mechanical equipment, solar energy panels, skylights, and any otherappurtenances, they are not part of the equation
4.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
Which of the following should be the next steps for a project that identified their site as contaminated through a local record?
The project should conduct a Phase 1 or Phase 2 environmental site assessment (or a local equivalent) to confirm contamination
The project should obtain a declaration from the authority having jurisdiction indicating the presence of contamination
The project should work with a biologist or environmental scientist to confirm contamination
The project should start remediation work
Answer explanation
The project could use one of the following to confirm contamination.
1) Consult local records
2) Conduct a Phase 1 or Phase 2 Environmental Site Assessment (or a local equivalent)
3) Work with a biologist or environmental scientist
Since it’s already identified as brown field through local records – the project doesn’t have to conduct another assessment
Next step should be obtaining a declaration from the authority having jurisdiction indicating the presence of contamination and working on remediation requirementsThe project cannot start remediation until and unless the contamination is declared from the authority having jurisdiction first and second, the project should work
with the jurisdiction to determine the remediation requirements. The third step is to remediate the project site to the satisfaction of the authority having jurisdiction
5.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
A new construction college campus project has decided on contouring the land to prevent damage due to erosion. Which of the following is required to achieve SS Prerequisite 1- Construction Activity Pollution Prevention?
Transportation Management Plan.
Best Management Practices Plan
Confirmation that the post-development runoff rate does not exceed the pre-development runoff rate
Confirmation that the project complies with NPDES or local regulations whichever is more stringent
Answer explanation
The project would have to provide confirmation it complies with NPDES or a local regulation, whichever is more stringent, to qualify for SS Prerequisite Construction Activity Pollution Prevention.
6.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
For SS Credit SS Credit Site Development – Protect or Restore Habitat – Option 1 – On-Site Restoration, the restored soil must meet which of the following criteria of reference soils?
Compaction only
Soil chemical characteristics only
Infiltration rates and compaction only
Organic matter, compaction, infiltration rates, soil biological function and soil chemical characteristics
Answer explanation
Restored soil must meet the criteria of reference soils in categories 1–3 and meet the criteria of either category 4 or 5:
1. organic matter
2. compaction
3. infiltration rates
4. soil biological function
5. soil chemical characteristics
7.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
A LEED Project Team is planning to landscape their project which is on a graded site. The project site area is 120,000 sq. ft and the building footprint is 60,000 sq. ft. Which of the following actions need to be done to earn one point for SS Credit 2 – Site Development – Protect or Restore Habitat?
Landscape with native or adaptive vegetation to cover 36,000 sq. ft area
Landscape with native or adaptive vegetation to cover 24,000 sq. ft area
Limit all disturbances to thirty feet beyond constructed areas with permeable surfaces
Limit all disturbances to fifty feet beyond the building perimeter
Answer explanation
To earn credit with Site Development – Protect or Restore Habitat, landscape with native or adaptive vegetation must cover 36,000 sq. ft. area. (Using native or adapted vegetation, projects should restore 30% (including the building footprint) of all portions of the site identified as previously developed)
Create a free account and access millions of resources
Popular Resources on Wayground
25 questions
Equations of Circles

Quiz
•
10th - 11th Grade
30 questions
Week 5 Memory Builder 1 (Multiplication and Division Facts)

Quiz
•
9th Grade
33 questions
Unit 3 Summative - Summer School: Immune System

Quiz
•
10th Grade
10 questions
Writing and Identifying Ratios Practice

Quiz
•
5th - 6th Grade
36 questions
Prime and Composite Numbers

Quiz
•
5th Grade
14 questions
Exterior and Interior angles of Polygons

Quiz
•
8th Grade
37 questions
Camp Re-cap Week 1 (no regression)

Quiz
•
9th - 12th Grade
46 questions
Biology Semester 1 Review

Quiz
•
10th Grade