TIAPMP

TIAPMP

Professional Development

10 Qs

quiz-placeholder

Similar activities

Good Morning! Let's Feedforward!

Good Morning! Let's Feedforward!

Professional Development

10 Qs

TownHall

TownHall

Professional Development

10 Qs

Leader As Coach

Leader As Coach

Professional Development

10 Qs

LUX - DAY 2

LUX - DAY 2

Professional Development

10 Qs

Call Center Quiz 2

Call Center Quiz 2

Professional Development

10 Qs

Pre-Placement Talk - St. Joseph University

Pre-Placement Talk - St. Joseph University

Professional Development

10 Qs

Pre test food and beverage service camp 6

Pre test food and beverage service camp 6

Professional Development

10 Qs

Smartness Test LBSV 2 March

Smartness Test LBSV 2 March

Professional Development

10 Qs

TIAPMP

TIAPMP

Assessment

Quiz

Professional Development

Professional Development

Hard

Created by

Dedy Hartanto

FREE Resource

AI

Enhance your content

Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...

10 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

While working on a construction project, one of the vendors is having an issue delivering a major component of the project. The vendor wants to replace that component with a similar working component. <br /><br />What should the project manager do in this situation?
Replace the vendor with someone that could get the correct component
Tell the vendor it’s okay to replace the component
Use expert judgment and determine if this alternative component is acceptable
Instruct the vendor to use the original component even if it delays the schedule

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

While working on a software development agile project, a team member is having difficulty with some of the work. The project manager has done some research and has determined that this is due to the lack of knowledge by the team member. <br /><br />What should the project manager do in this situation?
Instruct the team member on how to fix the problem
Replace the team member with someone with the correct knowledge
Meet with the project team and have them come up with a solution to solve the issue
<br />Reassign the team member to another part of the project

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The project sponsor has requested a major change to one of the deliverables. The team agrees the change should be implemented but disagrees on the method of implementation. <br /><br />What should the project manager do in this situation?
Submit the change to the Change Control Board for approval
Meet with the Change Control Board and have them determine how to implement the change
Inform the sponsor that complex changes will require more time to implement
Meet with the team members to brainstorm ideas on how to implement the change

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

During a hybrid project, two teams, one using traditional and the other using hybrid, are creating critical components for the project. The two teams are working in parallel and depend on each other for information. You came to realize the two teams are not communicating and this could lead to a delay on the project. <br /><br />What should the project manager do in this situation?
Remove both teams and replace them with new teams that can work with each other
Allow them to keep working, as they will resolve it themselves
Have both teams meet to discuss the problem while you coach them to implement a solution to any issues
Have each team submit the issue to you, then implement a solution base on the issues

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

An organization has informed the project manager that the new product development project needs to be pushed out to the customers within eight months. The project manager alerts the sponsor that the estimated time is 36 months for completion. <br /><br />What should the project manager do in this situation?
Change the project to a hybrid method and ensure the team understand the deadline
Change the project to agile methods and utilize a minimum viable product approach
Change the project to an agile method ensure the product backlog does not change
Hire additional resources and conduct fast tracking and crashing to complete it sooner

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

While working on a hybrid product development project, a senior stakeholder has informed the project manager that he would like the project to be terminated instantly. If not, he will work with senior management to ensure everyone is terminated from the organization if the project does not stop right away. <br /><br />What should the project manager do first in this situation?
Schedule a one-on-one meeting with this senior stakeholder to learn more about this issue
Ask for a meeting with the organization’s senior management to report this stakeholder
Inform the team and tell them to be prepared to stop the project
Immediately schedule a meeting with the project sponsor to update him on the situation

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

An organization has just implemented an agile project to create a proof-of-concept product for its release to the market. A senior manager has informed the project manager that timing is the most critical part of this. <br /><br />What should the project manager emphasize the most on this project?
A project management plan the team can follow
Strict scope change process
Strict cost change processes
Working with the team to implement quicker iterations

Create a free account and access millions of resources

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

By signing up, you agree to our Terms of Service & Privacy Policy

Already have an account?

Discover more resources for Professional Development