EV Management

EV Management

University

5 Qs

quiz-placeholder

Similar activities

Introduction to Brand Management

Introduction to Brand Management

University - Professional Development

10 Qs

Financial Management Quiz - 3

Financial Management Quiz - 3

University

10 Qs

Master Budgeting

Master Budgeting

University

10 Qs

Qantas ACC1200

Qantas ACC1200

University

10 Qs

Scrum 101: The Introduction

Scrum 101: The Introduction

University

10 Qs

RIsk Management

RIsk Management

University

10 Qs

Summer Exam 3 Review

Summer Exam 3 Review

University

10 Qs

Freelancer Service Proposal & Pricing

Freelancer Service Proposal & Pricing

12th Grade - Professional Development

10 Qs

EV Management

EV Management

Assessment

Quiz

Business

University

Hard

Created by

Malak Attia

Used 2+ times

FREE Resource

5 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

The first step in the project control process for measuring and evaluating project performance is to

set a baseline plan

determine the project objectives.

determine the project deliverables

analyze the project budget

analyze the project budget

Answer explanation

The project control steps for measuring and evaluating project performance are first to set a baseline plan, then to measure progress and performance, next to compare plan against actual and finally taking action

2.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

A project manager just received the following information on her project: PV = 300, EV = 300, AC = 200. In terms of cost at completion(CPI)

the project will currently finish under budget, assuming the project continues to perform in this way.

the project will currently finish over budget, assuming the project continues to perform in this way.

the project will currently finish on budget, assuming the project continues to perform in this way.

the project will currently finish behind schedule, assuming the project continues to perform in this way.

there is insufficient information to draw conclusions.

Answer explanation

Since the EV is greater than the AC, at this time, the project is expected to finish under budget

3.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

The second step in the project control process for measuring and evaluating project performance is to

review the baseline plan with top management

analyze inputs to control system

compare plan against actual

measure progress and performance

review spending with team members.

Answer explanation

The project control steps for measuring and evaluating project performance are first to set a baseline plan, then to measure progress and performance, next to compare plan against actual and finally taking action

4.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

A team leader tells the project manager that as of right now, $1.20 worth of work has been accomplished for each $1 worth of scheduled work. The team leader got this information from viewing the

SV

TCPI

CPI

SPI

PCIB

Answer explanation

An SPI of 1.2 would tell the team leader that $1.20 worth of work has been accomplished for each $1 worth of scheduled work.

5.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

The earned value of a project is the

project cost to date adjusted for project scope changes.

total project cost to date.

cost incurred minus the planned cost.

estimated cost that has been earned by work that is completed

the planned time-phased baseline of the value of work scheduled

Answer explanation

Earned value for a task is simply the percent complete multiplied by the original budget. Stated differently, EV is the percent of the original budget that has been earned by actual work completed.