CPP 1

Quiz
•
Professional Development
•
Professional Development
•
Hard
Ian Dixon
Used 4+ times
FREE Resource
30 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
With reference to a large job with all trades in attendance, which one of the following
information sources states who is responsible for cutting holes in walls and floors, for systems pipework?
Job specification.
Site plan.
Water Regulations.
Installation plan
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
An extension light with a bulb protector of unbreakable glass or wire cage will usually be
required when working
in bathrooms
in roof spaces
in a kitchen
on sheet lead
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A pre-installation inspection of an occupied dwelling, where a new bathroom suite is to be
installed, reveals dirt marks on the landing wall. These are brought to the attention of the
customer who states that it does not matter as they are going to re-decorate. The correct
action would be to
record that this has been brought to the customer’s attention, but not report to the job
supervisor, because it will not be a problem
carry on with the work without taking any further action
try to be helpful to the customer and attempt to remove the marks
record that this has been brought to the customer’s attention and report the facts to the immediate job supervisor
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A cast iron bath needs to be moved to the first floor bathroom in an occupied private property.
Which of the following actions should be taken?
Remove the stairs to permit the bath to be lifted to the first floor location
Build a timber crate around the bath to help with the lifting process.
Carefully cover all the carpeted surfaces with thick dust sheets.
No particular actions are necessary.
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Upon completion of the plumbing installations on an estate of new dwellings, each homeowner must be provided with
the appliance operating instructions
the site plan showing the position of their house on the site
copies of all material delivery notes for work on their house
copies of the work schedules for work on their house.
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A delivery advice note is provided by the
customer to let the supplier know when to deliver materials
customer to confirm the details of the materials required
supplier to confirm the number and type of materials that are delivered
customer to show the delivery address for materials.
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which one of the following documents states the exact price that a plumber’s merchant will
supply materials for?
Estimate.
Specification.
Invoice.
Quotation.
Create a free account and access millions of resources
Similar Resources on Wayground
31 questions
D51 QUIZ OF THE DAY

Quiz
•
Professional Development
30 questions
D42 FACE THE CHALLENGE

Quiz
•
Professional Development
25 questions
New Others Test #1

Quiz
•
Professional Development
25 questions
Processes 6035-02 | Part 2

Quiz
•
Professional Development
25 questions
Processes 6035-02 | Part 1

Quiz
•
Professional Development
26 questions
D54 CHECK YOUR LEVEL

Quiz
•
Professional Development
32 questions
D63 QUIZ OF THE DAY

Quiz
•
Professional Development
25 questions
Ujian PMR

Quiz
•
Professional Development
Popular Resources on Wayground
10 questions
Lab Safety Procedures and Guidelines

Interactive video
•
6th - 10th Grade
10 questions
Nouns, nouns, nouns

Quiz
•
3rd Grade
10 questions
9/11 Experience and Reflections

Interactive video
•
10th - 12th Grade
25 questions
Multiplication Facts

Quiz
•
5th Grade
11 questions
All about me

Quiz
•
Professional Development
22 questions
Adding Integers

Quiz
•
6th Grade
15 questions
Subtracting Integers

Quiz
•
7th Grade
9 questions
Tips & Tricks

Lesson
•
6th - 8th Grade