1.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
A payment claim by a Contractor must be made before a payment is made.
True
False
2.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
An early payment claim by a Contractor will entitle him to an early payment.
True
False
3.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
The SOP Act seeks to supercede the contract provisions if the terms are not reasonable.
True
False
4.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
Under the SOP Act, a building contractor can apply for ________ to claim for work done that is unpaid.
arbitration
mediation
conciliation
adjudication
5.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
The SOP Act requires an Employer to respond within a maximum of _____ days after a payment claim is received.
7
14
21
28
6.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
If a contract does not provide for the date of payment response, the SOP Act will require the Employer to make payment within _______ days after a payment claim is served.
7
14
21
28
7.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
Under the PSSCOC form of contract, a contract administrator is required to issue the Payment Certificate within ___ days upon the receipt of the Contractor's payment claim.
7
14
21
28
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?