1.
MULTIPLE CHOICE QUESTION
5 mins • 1 pt
The diagram shows the activities required to complete a factory process. A forward scan has been completed for the process.
The duration of activity H is missing. What value should appear?
13
14
15
16
2.
MULTIPLE CHOICE QUESTION
3 mins • 1 pt
The diagram shows the activities required to complete a factory process. A forward scan has been completed for the process.
When a backward scan is completed, what is the value of X?
20
22
24
25
3.
MULTIPLE CHOICE QUESTION
3 mins • 1 pt
The diagram shows the activities required to complete a factory process. A forward scan has been completed for the process.
What is the critical path?
ABJ
AEGJ
CDGJ
CDHJ
4.
MULTIPLE CHOICE QUESTION
3 mins • 1 pt
The diagram shows the activities required to complete a task from start to finish and each activity has the duration (in days) shown beside it.
What is the EST (Earliest starting time) for activity Q?
23
27
28
29
5.
MULTIPLE CHOICE QUESTION
3 mins • 1 pt
The diagram shows the activities required to complete a process from start to finish and each activity has a duration (in days) shown beside it.
What is the critical path?
IKLPQ
IJMPQ
IJMNOQ
IKLNOQ
6.
MULTIPLE CHOICE QUESTION
3 mins • 1 pt
The diagram shows the activities required to complete a process from start to finish and each activity has a duration (in days) shown beside it.
What is the float time for activity K?
1 day
2 days
3 days
4 days
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A network flow diagram is shown.
Find the total weight of the cut labelled 1.
88
96
98
104
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?
Similar Resources on Wayground
10 questions
Pasca Higher Exponent
Quiz
•
9th - 12th Grade
10 questions
Modulus and Functions (Part1)
Quiz
•
12th Grade
12 questions
FEB QIIZ
Quiz
•
1st Grade - University
11 questions
Probability (HSC Q's?)
Quiz
•
12th Grade
10 questions
Scientist who work mathematic
Quiz
•
9th - 12th Grade
10 questions
Vectors
Quiz
•
11th - 12th Grade
14 questions
Graduation Quiz
Quiz
•
12th Grade
10 questions
The Brain Quiz - Demo(Practice) Round (Carries No Value)
Quiz
•
1st - 12th Grade
Popular Resources on Wayground
15 questions
Fractions on a Number Line
Quiz
•
3rd Grade
20 questions
Equivalent Fractions
Quiz
•
3rd Grade
25 questions
Multiplication Facts
Quiz
•
5th Grade
29 questions
Alg. 1 Section 5.1 Coordinate Plane
Quiz
•
9th Grade
22 questions
fractions
Quiz
•
3rd Grade
11 questions
FOREST Effective communication
Lesson
•
KG
20 questions
Main Idea and Details
Quiz
•
5th Grade
20 questions
Context Clues
Quiz
•
6th Grade
Discover more resources for Mathematics
20 questions
SSS/SAS
Quiz
•
9th - 12th Grade
14 questions
Making Inferences From Samples
Quiz
•
7th - 12th Grade
23 questions
CCG - CH8 Polygon angles and area Review
Quiz
•
9th - 12th Grade
20 questions
Domain and Range Spiral Review
Quiz
•
9th - 12th Grade
10 questions
Dividing a polynomial by a monomial
Quiz
•
10th - 12th Grade
16 questions
Explore Triangle Congruence Theorems
Quiz
•
9th - 12th Grade
17 questions
Interpreting Graphs Of Functions
Quiz
•
8th - 12th Grade
15 questions
Explore Exponential Functions and Their Applications
Quiz
•
9th - 12th Grade