PMP Exam Preparation - Ch 9 and 12 -Resource and Procurement

Quiz
•
Education
•
KG
•
Medium
quiz eNetwoQ
Used 6+ times
FREE Resource
10 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
2.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
3.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
4.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
4. The project manager and the team have come up with a few different criteria they will use when selecting a seller. The criteria include costs, qualifications, licenses, and financial stability of the seller. What best describes these criteria?
A. Procurement Documents
B. Agreement
C. Request for Proposal
D. Source Selection Criteria
5.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
5. While working on the office renovation project, the project manager has received multiple bids from different vendors. What the project manager thought would be a cost-effective contract turned out to be very expensive. The project manager then hires a professional estimator to determine what the contract should cost. What is the project manager looking for?
A. Outside estimate
B. Building Cost estimate
C. Independent Cost Estimate
D. PMO
6.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
6. Two project team members have had frequent clashes, which have at times resulted in shouting matches during teammeetings. The project manager has intervened, asked them to resolve their differences, and even facilitated a meetingbetween them, but things have gotten worse. The project manager is concerned that the situation is negatively affecting teamcohesion and is placing the successful completion of the project at risk.
What should the project manager do next?
A. Use formal procedures including disciplinary actions
B. Allow the team members to resolve their differences on their own
C. Facilitate another meeting between the two team members
D. Request that the other project team members intercede as a form of peer pressure
7.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
7. Late in a project, a key team member leaves the company. The project manager realizes that he does not have enough teammembers to meet the hard deadline. At a weekly status meeting, the project manager discusses several options with hisproject team, including authorizing additional overtime, hiring subcontractors, or bringing in additional resources from anotherproject team within the company.
Which resource management technique does the project manager use?
A. Cost-benefit analysis
B. Alternatives analysis
C. Problem solving
D. Interpersonal skills
Create a free account and access millions of resources
Similar Resources on Quizizz
10 questions
Day 3 - Quiz Review D1 & D2

Quiz
•
University
10 questions
Type of Group and Teams

Quiz
•
University
11 questions
IPM - Chapter 7 (Cost Management)

Quiz
•
University
10 questions
PMP Exam Preparation-eNetwoQ-Ch 1, 2 and 3 Introduction

Quiz
•
KG
10 questions
PMP Exam Preparation - Ch 12 Project Procurement Management

Quiz
•
KG
11 questions
Project Planning

Quiz
•
1st - 5th Grade
10 questions
PMP Study Group - Agile

Quiz
•
KG
10 questions
PMP Exam Mentoring Ch 7 Project Cost Management

Quiz
•
KG
Popular Resources on Quizizz
15 questions
Multiplication Facts

Quiz
•
4th Grade
20 questions
Math Review - Grade 6

Quiz
•
6th Grade
20 questions
math review

Quiz
•
4th Grade
5 questions
capitalization in sentences

Quiz
•
5th - 8th Grade
10 questions
Juneteenth History and Significance

Interactive video
•
5th - 8th Grade
15 questions
Adding and Subtracting Fractions

Quiz
•
5th Grade
10 questions
R2H Day One Internship Expectation Review Guidelines

Quiz
•
Professional Development
12 questions
Dividing Fractions

Quiz
•
6th Grade