PMP Exam Mentoring Ch 7 Project Cost Management
Quiz
•
Education
•
KG
•
Medium
quiz eNetwoQ
Used 14+ times
FREE Resource
Enhance your content
10 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
1.Early in the project’s planning phase, the project team determined that the cost to install the server would be $15,000. This is a high-level estimate, and the team thinks it may cost up to $10,000 more.
What kind of estimate is this?
A. Definitive estimate
B. Rough order of magnitude estimate
C. Wide Estimate
D. Plan Estimate
2.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
2. A team of efficiency experts hired by your company has concluded that the transportation costs associated with yourproject are excessive. You have been requested by the sponsor to cut the costs.
What is your best course of action?
A. Perform a root cause analysis
B. Conduct a cost reduction analysis
C. Carry out a trend analysis
D. Fast tracking
3.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
3. You are planning a research and development project, and you need to determine how the project costs will beestimated, budgeted, managed, monitored, and controlled. To complete this process, you need to know if there are any preapproved financial resources from which the detailed project costs can be developed.
What should you do next?
A. Consult the cost management plan
B. Review the project charter
C. Examine the basis of estimates for the project
D. Check the cost baseline
4.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
4. While working on a game design project, the project sponsor has asked the project manager that to ensure that his estimates are very precise.
What estimating technique should the project manager use?
A. Analogous Estimate
B. Bottom-up estimating
C. Accuracy Estimating
D. Oversight Estimating
5.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
5. A company must decide between renovating an existing building or constructing a new one. Each approach would requirean initial investment of $250,000. The renovation has a payback period of 2.5 years whereas the new construction has apayback period of 4.5 years. Your company president would need to make the final decision. All else being equal, which approach should you recommend as the better investment?
A. The construction of a new office building
B. The renovation of the current office building
C. There is not enough information to make a decision
D. Both options are equal since the initial investment is the same
6.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
6. You are managing a hotel construction project, and you have asked your project team to calculate the current earnedvalue metrics to determine the project performance. Your team reports back that the project's to-complete performanceindex (TCPI) is 0.9 based on the budget at completion (BAC).
Which of the following is true regarding your project's current situation as reflected by this TCPI value?
A. The project is within budget
B. The project is over budget
C. The project is behind schedule
D. The project is ahead of schedule
7.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
7. During project initiation, the project manager had provided an initial estimate of $250,000 with a range of -25% to +75%.The project is now in planning, and, as part of the Estimate Costs process, the project manager has to refine this estimateto a much narrower range.
How should the project manager determine the estimating methods that can be used and the accuracy required for thecost estimate?
A. Review the cost management plan
B. Examine the basis of estimates
C. Contact the finance department
D. Check the project charter
Create a free account and access millions of resources
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple

Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?
Similar Resources on Wayground
15 questions
Corporate investments and project business
Quiz
•
6th - 8th Grade
12 questions
Front office Organization
Quiz
•
University
11 questions
Scratch Quiz ADVANCED
Quiz
•
5th - 8th Grade
15 questions
Pert 1 SIMSP
Quiz
•
University
10 questions
Using Front End Estimation to Add
Quiz
•
4th Grade
10 questions
PMP Exam Mentoring - Ch 6 Project Schedule Management
Quiz
•
KG
10 questions
PMP Exam Study Group - Chapter 6 Schedule
Quiz
•
KG
7 questions
Project Management & Leadership
Quiz
•
University
Popular Resources on Wayground
20 questions
Brand Labels
Quiz
•
5th - 12th Grade
10 questions
Ice Breaker Trivia: Food from Around the World
Quiz
•
3rd - 12th Grade
25 questions
Multiplication Facts
Quiz
•
5th Grade
20 questions
ELA Advisory Review
Quiz
•
7th Grade
15 questions
Subtracting Integers
Quiz
•
7th Grade
22 questions
Adding Integers
Quiz
•
6th Grade
10 questions
Multiplication and Division Unknowns
Quiz
•
3rd Grade
10 questions
Exploring Digital Citizenship Essentials
Interactive video
•
6th - 10th Grade
Discover more resources for Education
20 questions
Disney Characters
Quiz
•
KG
11 questions
NFL Football logos
Quiz
•
KG - Professional Dev...
20 questions
Place Value
Quiz
•
KG - 3rd Grade
10 questions
Movie Trivia
Quiz
•
KG - 2nd Grade
20 questions
Logos
Quiz
•
KG
6 questions
Things that can move.
Quiz
•
KG
15 questions
Pronouns
Quiz
•
KG - 3rd Grade
15 questions
The Five Senses
Quiz
•
KG