PMP Exam Mentoring - Ch 6 Project Schedule Management
Quiz
•
Education
•
KG
•
Hard
quiz eNetwoQ
Used 32+ times
FREE Resource
10 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
2.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
3.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
3. After an agile team completes three iterations, the project manager determines that the average velocity of the team for thesethree iterations was 30 story points. There are 292 more story points to complete the remaining portion of the project.
How many additional iterations will it take for the team to complete the project?
A. 7 iterations
B. 8 iterations
C. 9 iterations
D 10 iterations
4.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
4. After the project team has completed their first iteration, you are requested to provide the project's status report to thesponsor. You collect the following data:
The cost baseline for the entire project is $528,000
The schedule baseline provides for six two-week iterations<br />The actual costs associated with the first iteration were $80,000
The team completed 45 of 50 story points planned for the first iteration
What should you report to the sponsor?
A. The team's velocity in the first iteration is zero
B. The team's velocity in the first iteration is 50
C. The SPI for the first iteration is 0.9
D. The CPI for the first iteration is 1.1
5.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
5. A project manager is estimating the length of time the project will take. The project manager worked on a comparable projecttwo years ago that installed 10 miles of guardrails at a rate of one mile a day in similar weather conditions, using the samesize crew on the same type of highway.
What estimating technique would be the appropriate option for the project manager to use for his duration estimate?
A. Parametric estimating
B. Analogous estimating
C. Bottom-up estimating
D. Three-point estimating
6.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
6. An agile project to develop a new application has just finished its first iteration. To better assess marketing and support needs, the company's management has requested that the scrum master provide a date for when the application can belaunched.
What is the best course of action for the scrum master?
A. Provide an accurate estimate based on the velocity of the first iteration
B. Request time to develop the project schedule baseline
C. If possible, defer estimating until after a few iterations are completed
D. Provide a random date just to calm the management down
7.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
7. A project manager has just calculated the project performance measurements, and the project's current cost performanceindex (CPI) is 0.9 while the schedule performance index (SPI) is 1.1.
Which of the following is correct regarding the project's performance status?
A. Over budget and ahead of schedule
B. Under budget and behind schedule
C. Over budget and behind schedule
D. Under budget and ahead of schedule
Create a free account and access millions of resources
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple

Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?
Similar Resources on Wayground
10 questions
PMP Exam Mentoring Ch 8 Project Quality Management
Quiz
•
KG
10 questions
PMP Exam Preparation Mentoring Ch 4 Integration
Quiz
•
KG
10 questions
sample quiz
Quiz
•
University
11 questions
Intro to Adobe Premiere Pro 2023
Quiz
•
9th - 12th Grade
15 questions
Communication Skills
Quiz
•
9th - 12th Grade
10 questions
Hari 3 - Kuis Coding & Perkenalan AI
Quiz
•
KG - University
10 questions
Production Steps of a Project
Quiz
•
9th - 12th Grade
15 questions
Lession 47 - Test-6
Quiz
•
5th - 8th Grade
Popular Resources on Wayground
20 questions
Brand Labels
Quiz
•
5th - 12th Grade
10 questions
Ice Breaker Trivia: Food from Around the World
Quiz
•
3rd - 12th Grade
25 questions
Multiplication Facts
Quiz
•
5th Grade
20 questions
ELA Advisory Review
Quiz
•
7th Grade
15 questions
Subtracting Integers
Quiz
•
7th Grade
22 questions
Adding Integers
Quiz
•
6th Grade
10 questions
Multiplication and Division Unknowns
Quiz
•
3rd Grade
10 questions
Exploring Digital Citizenship Essentials
Interactive video
•
6th - 10th Grade
Discover more resources for Education
20 questions
Disney Characters
Quiz
•
KG
11 questions
NFL Football logos
Quiz
•
KG - Professional Dev...
20 questions
Place Value
Quiz
•
KG - 3rd Grade
10 questions
Movie Trivia
Quiz
•
KG - 2nd Grade
20 questions
Logos
Quiz
•
KG
6 questions
Things that can move.
Quiz
•
KG
15 questions
Pronouns
Quiz
•
KG - 3rd Grade
15 questions
The Five Senses
Quiz
•
KG