PMP Exam Mentoring - Ch 6 Project Schedule Management

Quiz
•
Education
•
KG
•
Hard
quiz eNetwoQ
Used 31+ times
FREE Resource
10 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
2.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
3.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
3. After an agile team completes three iterations, the project manager determines that the average velocity of the team for thesethree iterations was 30 story points. There are 292 more story points to complete the remaining portion of the project.
How many additional iterations will it take for the team to complete the project?
A. 7 iterations
B. 8 iterations
C. 9 iterations
D 10 iterations
4.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
4. After the project team has completed their first iteration, you are requested to provide the project's status report to thesponsor. You collect the following data:
The cost baseline for the entire project is $528,000
The schedule baseline provides for six two-week iterations<br />The actual costs associated with the first iteration were $80,000
The team completed 45 of 50 story points planned for the first iteration
What should you report to the sponsor?
A. The team's velocity in the first iteration is zero
B. The team's velocity in the first iteration is 50
C. The SPI for the first iteration is 0.9
D. The CPI for the first iteration is 1.1
5.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
5. A project manager is estimating the length of time the project will take. The project manager worked on a comparable projecttwo years ago that installed 10 miles of guardrails at a rate of one mile a day in similar weather conditions, using the samesize crew on the same type of highway.
What estimating technique would be the appropriate option for the project manager to use for his duration estimate?
A. Parametric estimating
B. Analogous estimating
C. Bottom-up estimating
D. Three-point estimating
6.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
6. An agile project to develop a new application has just finished its first iteration. To better assess marketing and support needs, the company's management has requested that the scrum master provide a date for when the application can belaunched.
What is the best course of action for the scrum master?
A. Provide an accurate estimate based on the velocity of the first iteration
B. Request time to develop the project schedule baseline
C. If possible, defer estimating until after a few iterations are completed
D. Provide a random date just to calm the management down
7.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
7. A project manager has just calculated the project performance measurements, and the project's current cost performanceindex (CPI) is 0.9 while the schedule performance index (SPI) is 1.1.
Which of the following is correct regarding the project's performance status?
A. Over budget and ahead of schedule
B. Under budget and behind schedule
C. Over budget and behind schedule
D. Under budget and ahead of schedule
Create a free account and access millions of resources
Similar Resources on Quizizz
15 questions
Pembelajaran Ms Project

Quiz
•
Professional Development
10 questions
PMP SG Ch 6 Schedule Post Test

Quiz
•
KG
10 questions
PMP Exam - Study Group Ch Quality and Resources

Quiz
•
KG
10 questions
PMP Exam Preparation Mentoring - Agile Session

Quiz
•
KG
15 questions
PM Project Baseline

Quiz
•
11th Grade
10 questions
PMP Study Group Chapter Project Scope Management

Quiz
•
KG
10 questions
PMP Exam Study Group Pretest Ch 11 Project Risk Management

Quiz
•
KG
10 questions
PMP Exam Preparation Mentoring Ch 5 Project Scope Management

Quiz
•
KG
Popular Resources on Quizizz
15 questions
Multiplication Facts

Quiz
•
4th Grade
25 questions
SS Combined Advisory Quiz

Quiz
•
6th - 8th Grade
40 questions
Week 4 Student In Class Practice Set

Quiz
•
9th - 12th Grade
40 questions
SOL: ILE DNA Tech, Gen, Evol 2025

Quiz
•
9th - 12th Grade
20 questions
NC Universities (R2H)

Quiz
•
9th - 12th Grade
15 questions
June Review Quiz

Quiz
•
Professional Development
20 questions
Congruent and Similar Triangles

Quiz
•
8th Grade
25 questions
Triangle Inequalities

Quiz
•
10th - 12th Grade