1.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
1. You gave the responsibility of collecting requirement from project stakeholder to four of your team members. After starting the requirement collection process, one of your team members left the job and the requirements could not be compiled properly. Initially, you did not notice this, however, during a product review, a few stakeholders told you that some of the features in the product were not requested by them. Therefore, to verify their comments you review the product requirements and identify the issue.
A. Scope creep
B. Scope slippage
C. Gold Scope
D. Opportunity
2.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
3.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
3. The client informs you that he noticed some parts of the work are not being completed by your team. You ensure him that you will look into it and give a proper response after verifying the facts.
Which document will you refer to verify it?
A. Project scope statement
B. WBS dictionary
C. Schedule baseline
D. WBS
4.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
4. - As the project manager for a large, complex project, you have been getting complaints from your team, including some of the management team, about all the time being spent on planning. You know that by spending time following the appropriate planning process, you can prevent many problems during execution. This will save time in the later stages of the project. One of the primary complaints you were hearing is related to the time it takes to create the Work Breakdown Structure (WBS). You are explaining the importance of the WBS to your project team members. Which of the following statements about the WBS is incorrect?
A. it is a hierarchical decomposition of Project work<br />
B. Planned work contained in the lowest level WBS components are called WBS dictionaries.<br />
C. The WBS subdivides the project work into smaller, more manageable pieces of work
D. The WBS organizes and defines the total scope of the project work
5.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
5. While finalizing the WBS, you assign each work package to a control account and establish a unique identified for the same work from a code of account. These identifiers help you find a hierarchical sum of costs, schedule, etc. Which statement is true about the WBS?
A. It contains all project work
B. It authorizes the project manager
C. It is a hierarchy of project staft
D. It is a hierarchical breakdown of project resources
6.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
6. During the collect requirement process, an influential stakeholder requested a Feature which was rejected. During the project execution, you notice that you have an opportunity to incorporate the requirement of this stakeholder into product and it will cost you nothing. By doing so, the stakeholder will be pleased and may help you in your next assignment. This is an example of:
A. Scope creep
B. Scope slippage
C. Gold plating
D. Opportunity
7.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
7. - In the the create WBS process, you sub-divide project deliverables and project work into smaller and more manageable components. The output of this process is the Scope Baseline and Project document updates.
Which of the following truly represents the scope baseline?
A. Scope statement, Scope management plan, Schedule baseline
B. Scope statement, WBS, WBS dictionary
C. WBS, WBS dictionary, Risk Register
D. Scope statement, WBS, Schedule baseline
Create a free account and access millions of resources
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple

Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?
Similar Resources on Wayground
11 questions
Education Concepts and Scope
Quiz
•
12th Grade
10 questions
Project Scope Statement
Quiz
•
11th Grade
10 questions
Risk Management
Quiz
•
University
8 questions
Hybrid Project Management - Quiz 2
Quiz
•
University
10 questions
Quiz WBS 06.03.2023
Quiz
•
Professional Development
10 questions
Post Session Quiz
Quiz
•
Professional Development
15 questions
Regional Immersion Project - 1
Quiz
•
Professional Development
10 questions
Project Management
Quiz
•
Professional Development
Popular Resources on Wayground
20 questions
Brand Labels
Quiz
•
5th - 12th Grade
10 questions
Ice Breaker Trivia: Food from Around the World
Quiz
•
3rd - 12th Grade
25 questions
Multiplication Facts
Quiz
•
5th Grade
20 questions
ELA Advisory Review
Quiz
•
7th Grade
15 questions
Subtracting Integers
Quiz
•
7th Grade
22 questions
Adding Integers
Quiz
•
6th Grade
10 questions
Multiplication and Division Unknowns
Quiz
•
3rd Grade
10 questions
Exploring Digital Citizenship Essentials
Interactive video
•
6th - 10th Grade
Discover more resources for Education
20 questions
Disney Characters
Quiz
•
KG
11 questions
NFL Football logos
Quiz
•
KG - Professional Dev...
20 questions
Place Value
Quiz
•
KG - 3rd Grade
10 questions
Movie Trivia
Quiz
•
KG - 2nd Grade
20 questions
Logos
Quiz
•
KG
6 questions
Things that can move.
Quiz
•
KG
15 questions
Pronouns
Quiz
•
KG - 3rd Grade
15 questions
The Five Senses
Quiz
•
KG