PMP Exam - Study Group Ch Quality and Resources

Quiz
•
Education
•
KG
•
Hard
quiz eNetwoQ
Used 9+ times
FREE Resource
10 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
1. Development team members argue with the product owner who rejected a deliverable the team developed during the recent iteration. The project manager schedules a meeting with the team, product owner, and other relevant stakeholders to breakdown the situation and identify the root cause of a misunderstanding.
Which of the following will be considered an antipattern if used during the meeting?
A. Drawing a fishbone diagram
B.Using the five whys method
C. Maximizing the number of action items
D. Defining the problem statement
2.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
2. As a project manager, you are leading a colocated project team that will create deliverables in an agile fashion, followed by a rollout phase that will use a predictive approach. You are concerned that the transition from agile to waterfall may cause friction within the project team.
With the development phase complete, how might the team's working agreements need to change in this situation?
A. The team charter will need to be updated to reflect collective responsibility for the completion of project tasks
B. The project manager should institute a set of working agreements that worked well on previous waterfall<br />projects.
C. Each project team member will need to develop their own social contract to support the new framework.
D. The social contract should reflect a transition from collective to individual responsibility for the project tasks.
3.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
3. At the sprint planning meeting, the scrum master reiterates that if by the end of the sprint the product increment that the agile project team is building does not meet the criteria specified at the beginning of the sprint, this work will not be included in the velocity for the current sprint.
What does the scrum master refer to?
A. Estimate to complete
B. Definition of done
C. Project exit criteria
D. Quality metrics
4.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
4. You are managing a virtual project team across multiple time zones. As the project progresses, the team members learn to trust one another and adjust their work routines to accommodate the different time zones, work habits, and culture.
What stage of team development is being demonstrated in this situation?
A.Forming
B. Storming
C. Performing
D. Norming
5.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
5. An agile team has just completed the development of the final project's deliverable. The team members are seeking advice from the project manager as to their next step.
What should the project manager advise the team to do next?
A. Determine the acceptance criteria
B. Ensure that the user stories meet the definition of ready (DoR)
C. Hold a project retrospective
D. Verify that the deliverables meet the definition of done (DoD)
6.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
6. As a scrum master, you are facilitating a retrospective for a sprint that failed to meet all of its objectives. Members of the development team and the product owner are arguing over who is responsible for the failure. After performing a root cause analysis, you uncover the source of the conflict.
Of the following, what did you most likely discover?
A. The product owner determined how many user stories were to be completed during the sprint
B. The development team decided how many user stories were to be completed during the sprint
C. You, as the scrum master, failed to assign user stories to the development team
D. The Gantt chart did not include enough story points
7.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
7. A project manager schedules a meeting for the scrum project team to reflect and adapt.
What will the participants be most likely doing at this meeting?
A. Demonstrating the product increment to the customer
B. Selecting user stories for the next sprint
C. Discussing the on-going work and impediments to progress
D. Looking for any improvements to the team's process
Create a free account and access millions of resources
Similar Resources on Wayground
10 questions
Day 3 - Quiz Review D1 & D2

Quiz
•
University
10 questions
Quiziz for "English for Physical Education Teachers"

Quiz
•
University
10 questions
PMP Study Group - Agile

Quiz
•
KG
6 questions
Project Methodology Quiz

Quiz
•
KG - Professional Dev...
10 questions
Agile

Quiz
•
University - Professi...
7 questions
Agile/Scrum

Quiz
•
1st Grade
10 questions
PMP Exam Mentoring Ch 7 Project Cost Management

Quiz
•
KG
10 questions
Introduction to SE (Part 2)

Quiz
•
University
Popular Resources on Wayground
11 questions
Hallway & Bathroom Expectations

Quiz
•
6th - 8th Grade
20 questions
PBIS-HGMS

Quiz
•
6th - 8th Grade
10 questions
"LAST STOP ON MARKET STREET" Vocabulary Quiz

Quiz
•
3rd Grade
19 questions
Fractions to Decimals and Decimals to Fractions

Quiz
•
6th Grade
16 questions
Logic and Venn Diagrams

Quiz
•
12th Grade
15 questions
Compare and Order Decimals

Quiz
•
4th - 5th Grade
20 questions
Simplifying Fractions

Quiz
•
6th Grade
20 questions
Multiplication facts 1-12

Quiz
•
2nd - 3rd Grade