Agile Metrics

Agile Metrics

Professional Development

20 Qs

quiz-placeholder

Similar activities

Project and Operations Management Quiz

Project and Operations Management Quiz

Professional Development

20 Qs

Lean Six Sigma (English)

Lean Six Sigma (English)

Professional Development

25 Qs

Enhance your Cloud Native Fundamentals - SPAIC (Quiz-2)

Enhance your Cloud Native Fundamentals - SPAIC (Quiz-2)

Professional Development

15 Qs

VQE/VSIM

VQE/VSIM

Professional Development

17 Qs

Agile Business Analysis

Agile Business Analysis

Professional Development

15 Qs

CTFL-U1_2_3_4-080422a

CTFL-U1_2_3_4-080422a

Professional Development

16 Qs

CTFL WHOLE 110822a

CTFL WHOLE 110822a

Professional Development

22 Qs

CTFL_U12345200522a

CTFL_U12345200522a

Professional Development

25 Qs

Agile Metrics

Agile Metrics

Assessment

Quiz

Other, Professional Development

Professional Development

Medium

Created by

PriLog s

Used 1+ times

FREE Resource

20 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following is an estimated cost for delivering a single point based on past performance of the delivering Organization?

Cost per point

Baseline Velocity

Product backlog in points

Planned Value

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following metrics captures the number of escaped defects found over a period of time?

Live Defects

Escaped Defects

Cycle Time

Story defects

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following is the average time between delivery of completed work items?

Velocity

Lead Time

Cycle Time

Lag Tim

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

If the planned value is 300 and earned value is 280, what is the SPI

580

20

1.07

0.933

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the one important metric that Burnup charts show that Burndown charts do not?

Burnup chats shows velocity

Burnup charts show the number of iterations

Burnup charts show total work

Burnup charts show project duration

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

If the CPI of a project is 1.1 and the SPI is 0.8, what is the inference about the project?

It is over budget and behind schedule

It is under budget and ahead of schedule

It is under budget and behind schedule

It is over budget and ahead of schedule

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A Project Team has completed three iterations and recorded a velocity of 25, 30 and 35 story points; the total Release backlog has 300 story points. How many iterations are required to complete the project?

10

7

8.5

12

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?