PROGRAMMING TECHNIQUES

PROGRAMMING TECHNIQUES

University - Professional Development

25 Qs

quiz-placeholder

Similar activities

Topic 6 EA : Authentic Assessments @ OUM

Topic 6 EA : Authentic Assessments @ OUM

University

20 Qs

Outsourcing Quiz

Outsourcing Quiz

University

20 Qs

Curriculum Development

Curriculum Development

University

20 Qs

Assessment 2 Quiz

Assessment 2 Quiz

University

20 Qs

Post Test Pelatihan Desain Pembelajaran Aktif BGP Riau

Post Test Pelatihan Desain Pembelajaran Aktif BGP Riau

Professional Development

20 Qs

Peng. Pemb. IPA SD UAS

Peng. Pemb. IPA SD UAS

University

20 Qs

2nd/Educ 7- Semi Final Examination (3rd year and Earners)

2nd/Educ 7- Semi Final Examination (3rd year and Earners)

University

20 Qs

Challenge "Ulasan PKKMB dan Materi Webinar"

Challenge "Ulasan PKKMB dan Materi Webinar"

University

20 Qs

PROGRAMMING TECHNIQUES

PROGRAMMING TECHNIQUES

Assessment

Quiz

Education

University - Professional Development

Practice Problem

Medium

Created by

PROFESOR ISA

Used 30+ times

FREE Resource

AI

Enhance your content in a minute

Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...

25 questions

Show all answers

1.

MULTIPLE SELECT QUESTION

45 sec • 1 pt

Choose the programming techniques used in planning and monitoring of project performance (you may choose more than one techniques)

Bar Chart

Line of Balance

Network Technique - CPM

Network Technique - Precedence

PERT - Programme Evaluation and Review Techniques

2.

MULTIPLE SELECT QUESTION

45 sec • 1 pt

What are the limitations of using Bar Chart?

Show relationships between project activities

Does not identify activities which control a project's total duration (i.e., critical activities comprising critical path)

Does not relate delay or change of one activity to the entire project

Can be used for large projects

3.

MULTIPLE SELECT QUESTION

45 sec • 1 pt

Media Image

A network is a graphical diagram as shown. Select important elements in a network

Arrows

Nodes

Activities

Duration

Resources

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Media Image

Select the correct description for the following network

Activity B must be completed before Activity A completed

Activity A must be completed before Activity B completed

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Media Image

Select the correct description for the network below

Activities A and B can occur concurrently, but both must be completed before Activity C can begin

Activity C must be completed before Activity A is completed

6.

MULTIPLE SELECT QUESTION

45 sec • 1 pt

The choice of Scheduling Method/Planning Techniques will depend on the followings

Familiarity on the technique to be used and acceptable by parties involved

Type and size of project

Purpose of scheduling

7.

MULTIPLE SELECT QUESTION

45 sec • 1 pt

Network analysis

is a method of project planning done on activities so that it is connected to each other

is used to optimized the usage of resources and also for monitoring and controlling

the purpose of network analysis is to ascertain the critical path for a certain project.

has a number of techniques for planning and control of projects

Create a free account and access millions of resources

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

By signing up, you agree to our Terms of Service & Privacy Policy

Already have an account?