COST and SCHEDULE

COST and SCHEDULE

Professional Development

35 Qs

quiz-placeholder

Similar activities

Cold Water Systems | 6035-02 | Picture Quiz

Cold Water Systems | 6035-02 | Picture Quiz

Professional Development

31 Qs

MSG PST Week 4 Refresher

MSG PST Week 4 Refresher

Professional Development

30 Qs

Comptia Sec+ 421-450

Comptia Sec+ 421-450

Professional Development

30 Qs

MGNF-32

MGNF-32

Professional Development

30 Qs

TRY OUT PPPK TEAM 12 SESI 1

TRY OUT PPPK TEAM 12 SESI 1

Professional Development

30 Qs

TRY OUT UKG 2019

TRY OUT UKG 2019

Professional Development

40 Qs

Nirmaan - Pariksha - Products

Nirmaan - Pariksha - Products

Professional Development

35 Qs

Đề 2 - 28053 032021

Đề 2 - 28053 032021

Professional Development

40 Qs

COST and SCHEDULE

COST and SCHEDULE

Assessment

Quiz

Professional Development

Professional Development

Hard

Created by

Achmad Fuad

Used 2+ times

FREE Resource

35 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

10 sec • 1 pt

One common way to compute estimate at completion (EAC) is to take the budget at completion (BAC) and:
Divide by SPI.
Multiply by SPI.
Multiply by CPI.
Divide by CPI.

2.

MULTIPLE CHOICE QUESTION

5 sec • 1 pt

Estimate at completion (EAC) is a periodic evaluation of:
The cost of work completed.
The value of work performed.
The anticipated total cost at project completion.
What it will cost to finish the project.

3.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

During the conceptual phase of a pipeline project, the project engineer estimates the following: the cost of the materials is most likely $100,000; optimistically $90,000; and pessimistically $120,000. The cost for labor is most likely $80,000; optimistically $70,000 and pessimistically $100,000. The cost for equipment is most likely $60,000; optimistically $50,000 and pessimistically $70,000. The cost for construction management fees is most likely $30,000; optimistically $20,000 and pessimistically $40,000. What is the probability of the project coming in under $270,000?

Less than 50%

Exactly 50%

Over 50%

Zero

4.

MULTIPLE CHOICE QUESTION

10 sec • 1 pt

A manufacturing project has a schedule performance index (SPI) of 0.89 and a cost performance index (CPI) of 0.91. Generally, what is the BEST explanation for why this occurred?
The scope was changed
Additional equipment needed to be purchased
A supplier went out of business and new one needed to be found
A critical path activity took longer and needed more labor hours to complete

5.

MULTIPLE CHOICE QUESTION

10 sec • 1 pt

A project manager is working with management to create the project estimate. During the initiating process group, what level of accuracy should the estimate have?
-10% to +10%
-25% to +75%
-35% to +75%
-10% to +25%

6.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

You are a project manager for a small construction project. Your project was budgeted for $72,000 over a six-week period. As of today, you’ve spent $22,000 of your budget to complete work that you originally expected would cost $24,000. According to your schedule, you should have spent $30,000 by this point. Based on these circumstances, your project could be BEST describe as:
Under budget
Over budget
On Budget
Not having enough information provided

7.

MULTIPLE CHOICE QUESTION

10 sec • 1 pt

You are about to take over a project from another project manager and find out the following information about the project: activity Z has an early start of day 15 and late start of day 20. Activity Z is difficult activity. Cost performance index is 1.1; schedule performance index is 0.8. There are 11 stakeholders on the project. Based on the information, which of the following would you be the MOST concerned about?
Schedule
Float
Cost
The number of available resources

Create a free account and access millions of resources

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

By signing up, you agree to our Terms of Service & Privacy Policy

Already have an account?

Discover more resources for Professional Development