COST and SCHEDULE
Authored by Achmad Fuad
Professional Development
Professional Development
Used 2+ times

AI Actions
Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...
Content View
Student View
35 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
10 sec • 1 pt
One common way to compute estimate at completion (EAC) is to take the budget at completion (BAC) and:
2.
MULTIPLE CHOICE QUESTION
5 sec • 1 pt
Estimate at completion (EAC) is a periodic evaluation of:
3.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
During the conceptual phase of a pipeline project, the project engineer estimates the following: the cost of the materials is most likely $100,000; optimistically $90,000; and pessimistically $120,000. The cost for labor is most likely $80,000; optimistically $70,000 and pessimistically $100,000. The cost for equipment is most likely $60,000; optimistically $50,000 and pessimistically $70,000. The cost for construction management fees is most likely $30,000; optimistically $20,000 and pessimistically $40,000. What is the probability of the project coming in under $270,000?
Less than 50%
Exactly 50%
Over 50%
Zero
4.
MULTIPLE CHOICE QUESTION
10 sec • 1 pt
A manufacturing project has a schedule performance index (SPI) of 0.89 and a cost performance index (CPI) of 0.91. Generally, what is the BEST explanation for why this occurred?
5.
MULTIPLE CHOICE QUESTION
10 sec • 1 pt
A project manager is working with management to create the project estimate. During the initiating process group, what level of accuracy should the estimate have?
6.
MULTIPLE CHOICE QUESTION
20 sec • 1 pt
You are a project manager for a small construction project. Your project was budgeted for $72,000 over a six-week period. As of today, you’ve spent $22,000 of your budget to complete work that you originally expected would cost $24,000. According to your schedule, you should have spent $30,000 by this point. Based on these circumstances, your project could be BEST describe as:
7.
MULTIPLE CHOICE QUESTION
10 sec • 1 pt
You are about to take over a project from another project manager and find out the following information about the project: activity Z has an early start of day 15 and late start of day 20. Activity Z is difficult activity. Cost performance index is 1.1; schedule performance index is 0.8. There are 11 stakeholders on the project. Based on the information, which of the following would you be the MOST concerned about?
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?