RitaBook2

RitaBook2

University

88 Qs

quiz-placeholder

Similar activities

VISUAL BASIC

VISUAL BASIC

University

84 Qs

Final Exam - Soft Eng 2

Final Exam - Soft Eng 2

University

85 Qs

User Support - chapter 9

User Support - chapter 9

University

83 Qs

Python Quiz - 6 BF

Python Quiz - 6 BF

University

88 Qs

spi final reviewer

spi final reviewer

University

93 Qs

Health and Safety#1

Health and Safety#1

University

90 Qs

OCR GCSE Computer Science - J276 1.1 - 1.7

OCR GCSE Computer Science - J276 1.1 - 1.7

KG - Professional Development

91 Qs

RitaBook2

RitaBook2

Assessment

Quiz

Computers

University

Medium

Created by

Orpheus Telos

Used 4+ times

FREE Resource

88 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

During project planning, you estimate the time needed for each activity and then total the estimates to create the project estimate. You commit to completing the project by this date. What is wrong with this scenario?

The team did not create the estimate, and estimating takes too long using that method

The team did not create the estimate, and a network diagram was not used

The estimate is too long and should be created by management

The project estimate should be the same as the customer's required completion date.

2.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

You are a project manager on a $5,000,000 software development project. While working with your project team to develop a network diagram, you notice a series of activities that can be worked in parallel but must finish in a specific sequence. What type of activity sequencing method is required for these activities?

Precedence diagramming method

Arrow diagramming method

Critical path method

Operational diagramming method

3.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

You are a project manager on a US $5,000,000 software development project. While working with your project team to develop a network diagram, your data architects suggest that quality could be improved if the data model is approved by senior management before moving on to other design elements. They support this suggestion with an article from a leading software development journal. Which of the following best describes this type of input?

Mandatory external dependency

Discretionary external dependency

External regulatory dependency

Heuristic

4.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Base on the following, if you needed to shorten the duration of the project, which activity would you try to shorten?

Activity: Start A B C D E F G H I

Preceding Activity: None Start Start Start A B,C C D E F G,H,I

Duration in Weeks: 0 1 2 6 10 1 2 3 9 1 0"

Activity B

Activity D

Activity H

Activity C

5.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

You have a project with the following activities: Activity A takes 40 hours and can start after the project starts.Activity B takes 25 hours and should happen after the project starts. Activity C must happen after activity A and takes 35 hours. Activity D must happen after activities B and C and takes 30 hours. Activity E must take place after activity C and takes 10 hours. Activity F takes place after Activity E and takes 22 hours. Activities F and D are the last activities of the project. Which of the following is true if activity B actually takes 37 hours?

The critical path is 67 hours

The critical path changes to Start, B, D, End

The critical path is Start, A, C, E, F, End.

The critical path increases by 12 hours

6.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

A project manager has received activity duration estimates from his team. Which of the following does he need in order to complete the Develop Schedule process?

Earned value analysis

Schedule change control system

Trend analysis

Reserves

7.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

A project manager is taking over a project from another project manager during project planning. If the new project manager wants to see what the previous project manager planned for managing changes to the schedule, it would be best to look at the:

Communications management plan

Update management plan

Staffing management plan

Schedule management plan

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?