20 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

PERT analysis is based on

Optimistic time

Pessimistic time

Most likely time

All the above.

2.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Which of the option is not a notable challenge while scheduling a project?

Deadlines exist.

Independent activities.

Too many workers may be required.

Costly delay

3.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

The particular task performance in CPM is known

Dummy

Event

Activity

Contract.

4.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

The earliest start time rule

Compares the activities starting time for an activity successor.

Compares the activities end time for an activity predecessor.

Directs when a project can start.

Regulates when a project must begin.

5.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

The critical path

Is a path that operates from the starting node to the end node

Is a mixture of all paths.

Is the longest path

Is the shortest path

6.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Completion of a CPM network diagram activity is commonly known

Connector

Event

Node

All the above.

7.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Activities A, B, and C are the immediate predecessors for Y activity. If the earliest finish times for the three activities are 12, 15, and 10, then the earliest start time for Y will be

10

15

12

Cannot be determined

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?