PMP Procurement Exercise

PMP Procurement Exercise

Professional Development

20 Qs

quiz-placeholder

Similar activities

Lazada PH Quiz 3: Finance

Lazada PH Quiz 3: Finance

Professional Development

20 Qs

Alestra Diagnóstico

Alestra Diagnóstico

Professional Development

15 Qs

Pre-Test Procurement Management

Pre-Test Procurement Management

Professional Development

20 Qs

Chapter 14: Overview of Conveyance Contracts

Chapter 14: Overview of Conveyance Contracts

Professional Development

16 Qs

Prof Prac (1)

Prof Prac (1)

Professional Development

25 Qs

Logistics and Supply Chain Management

Logistics and Supply Chain Management

Professional Development

15 Qs

Project Procurement Management

Project Procurement Management

Professional Development

20 Qs

Procurement Mngt W5 ProjIm

Procurement Mngt W5 ProjIm

Professional Development

17 Qs

PMP Procurement Exercise

PMP Procurement Exercise

Assessment

Quiz

Professional Development

Professional Development

Hard

Created by

Findi Darmawan

Used 21+ times

FREE Resource

20 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

You have been asked to assist the contract manager in drafting the contract for a large project with limited scope clarity. What type of contract would you suggest, such that your organization does not incur any financial losses ?

Time and Material

Fixed Price

Cost plus fixed fee

Cost plus incentive fee

2.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

A Cost Plus Incentive Fee (CPIF) contract has an estimated cost of $150K with a predetermined fee of $15K and a share ratio of buyer to seller equal to 70/30. The actual cost of the project is $120K. How much savings did the seller make in total, and out of total savings how much did he make because of the incentive ?

$30K, $9K

$55K, $30K

$32K, $27K

$15K, $3K

3.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

Which of the following is not an advantage of a fixed price contract ?

Less work for buyer to manage

Seller has a strong incentive to control cost

Buyer knows the total price at project start

Final cost may be more than a cost reimbursable contract because contractors have to inflate the price to cover their risk

4.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

A new project manager is about to begin creating the contract statement of work. One stakeholder wants to add many items to the contract statement of work. Another stakeholder only wants to describe the functional requirements. The project is important for the project manager's company, but a seller will do the work. How would you advise the project manager ?

The contract statement of work should be general to allow the seller to make his own decisions

The contract statement of work should be general to allow clarifications later

The contract statement of work should be detailed to allow clarification later

The contract statement of work should be as detailed as necessary for the type of project

5.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

A project manager for a large bank is in charge of developing a new certificate of deposit product, which needs information technology systems development. His internal information technology staff does not have expertise in the technology needed for this project, so he must contract out the work. Unfortunately, he does not have time or the information to develop a detailed contract statement of work, but this effort is likely to be large. In this situation, which is the best type of contract ?

Fixed price

Cost plus fixed fee

Cost plus incentive fee

Time and material

6.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

As the buyer during the contract negotiation process, you are interested in a contract that would have the least amount of risk to your organization. Which of the following contracts would be preferred to meet your risk-averse needs ?

Firm Fixed Price

Cost Plus Percentage of Cost

Cost Plus Incentive Fee

Cost Plus Fixed Fee

7.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

The buyer has negotiated a cost plus incentive fee contract with the seller. The contract has a target cost $300,000, a target fee of $40,000, a sharing ratio of 80/20, a maximum fee of $60,000 and a minimum fee of $10,000. If the actual cost of the project is $380,000 how much will the buyer pay as a fee to the seller ?

$56,000

$104,000

$30,000

$24,000

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?