Activity A has a pessimistic (P) estimate of 36 days, a most likely (ML) estimate of 21 days, and an optimistic (O) estimate of 6 days. What is the probability that activity A will be completed in 16 to 26 days?
PMP Exam Preparation Mocktest With Formula

Quiz
•
Professional Development
•
Professional Development
•
Hard
Gigih Suhartanto
Used 22+ times
FREE Resource
13 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
3 mins • 1 pt
55.70 percent
68.26 percent
95.46 percent
99.73 percent
2.
MULTIPLE CHOICE QUESTION
3 mins • 1 pt
Your lead engineer estimates that a work package will most likely require 50 weeks to complete. It could be completed in 40 weeks if all goes well, but it could take 180 weeks in the worst case. What is the expected duration of the work package?
45 weeks
70 weeks
90 weeks
140 weeks
3.
MULTIPLE CHOICE QUESTION
3 mins • 1 pt
What is the float for Activity G?
-2
0
1
4
4.
MULTIPLE CHOICE QUESTION
3 mins • 1 pt
If a project planner imposes a finish time of 14 on the project with no change in the start date or activity durations, what is the total float of Activity E?
–1
0
2
Cannot be determined
5.
MULTIPLE CHOICE QUESTION
3 mins • 1 pt
You are using earned value progress reporting for your current project in an effort to teach your software developers the benefits of earned value. You plan to display project results on the PMO dashboard so that the team knows how the project is progressing. Use the current status, listed below:
PV = $2,200
EV = $2,000
AC = $2,500
BAC = $10,000
According to earned value analysis, the SV and status of the project described above is—
–$300; the project is ahead of schedule
+$8,000; the project is on schedule
+$200; the project is ahead of schedule
–$200; the project is behind schedule
6.
MULTIPLE CHOICE QUESTION
3 mins • 1 pt
You are using earned value progress reporting for your current project in an effort to teach your software developers the benefits of earned value. You plan to display project results on the PMO dashboard so that the team knows how the project is progressing. Use the current status, listed below:
PV = $2,200
EV = $2,000
AC = $2,500
BAC = $10,000
What is the EAC for this project, and what does it represent?
$12,500; the revised estimate for total project cost (based on performance thus far)
$10,000; the revised estimate for total project cost (based on performance thus far)
$12,500; the original project budget
$10,000; the original project budget
7.
MULTIPLE CHOICE QUESTION
3 mins • 1 pt
If operations on a work package were estimated to cost $1,500 and finish today but, instead, have cost $1,350 and are only two-thirds complete, the cost variance is—
$150
–$150
–$350
–$500
Create a free account and access millions of resources
Similar Resources on Quizizz
8 questions
Quiz Lesson 5 - Topic C (Evaluate Project Progress)

Quiz
•
Professional Development
15 questions
All-In-One Project+ PK0-005 Exam Guide - Chapter 05

Quiz
•
Professional Development
10 questions
PMP - PROJECT INTEGRATION

Quiz
•
Professional Development
10 questions
All About Employee Engagement! (KDP Quiz)

Quiz
•
University - Professi...
10 questions
PMP PROJECT QUALITY MANAGEMENT

Quiz
•
Professional Development
13 questions
Project Initiation and Planning

Quiz
•
Professional Development
10 questions
Introduction to Project Management

Quiz
•
Professional Development
8 questions
PMC 2023 - The Importance of Planning in Project Mgmt

Quiz
•
Professional Development
Popular Resources on Quizizz
15 questions
Multiplication Facts

Quiz
•
4th Grade
20 questions
Math Review - Grade 6

Quiz
•
6th Grade
20 questions
math review

Quiz
•
4th Grade
5 questions
capitalization in sentences

Quiz
•
5th - 8th Grade
10 questions
Juneteenth History and Significance

Interactive video
•
5th - 8th Grade
15 questions
Adding and Subtracting Fractions

Quiz
•
5th Grade
10 questions
R2H Day One Internship Expectation Review Guidelines

Quiz
•
Professional Development
12 questions
Dividing Fractions

Quiz
•
6th Grade