In rolling wave planning:

Project Management 6(B)

Quiz
•
Other
•
University
•
Medium

El Awad Osman
Used 31+ times
FREE Resource
23 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
Focus is maintained on long-term objectives, allowing near-term objectives to be rolled out as part of the ongoing wave of activities.
The work to be accomplished in the near term is planned in detail, whereas the work in the future is planned at a higher level.
The work far in the future is planned in detail for work packages that are at a low level of the WBS.
A wave of detailed activities is planned during strategic planning to ensure that WBS deliverables and project milestones are achieved.
2.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
The precedence diagramming method (PDM) is:
A technique in which activities are represented by nodes and are graphically linked by one or more logical relationships to show the sequence in which the activities are to be performed.
A method that uses a probabilistic approach to scheduling project activities.
A time-phased graphical representation of the arrow diagramming method (ADM), and shows durations of project activities as well as their dependencies.
More accurate than the critical path method for scheduling when there are uncertainties about the durations of project activities.
3.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
The duration of the activity is affected by all of the following EXCEPT:
The estimated activity resource requirements.
The types of resources assigned to the activity.
The availability of the resources assigned to the activity.
Using the precedence diagramming method (PDM) for scheduling activities instead of using the critical path method (CPM).
4.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
A schedule compression technique used to shorten the schedule duration for the least incremental cost by adding resources is called:
Crashing.
Program evaluation and review technique (PERT).
Precedence diagramming method (PDM).
Fast tracking.
5.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
The “fast tracking” method of schedule compression involves:
The use of industrial engineering techniques to improve productivity, thereby finishing the project earlier than originally planned.
Performing in parallel for at least a portion of their duration activities or phases that are normally done in sequence, which may result in rework and increased risk.
Going on a “mandatory overtime schedule” to complete the project on schedule or earlier if possible.
Assigning “dedicated teams” to critical path activities to achieve project schedule objectives.
6.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
An example of a mandatory dependency is:
A dependency established based on knowledge of best practices within a particular application area.
A dependency established based on some unusual aspect of the project where a specific sequence is desired.
On a construction project, to erect the superstructure only after the foundation has been built.
On a software development project, to start design only after completion and approval of all project requirements.
7.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
Inputs to the Define Activities process are:
Schedule management plan, work breakdown structure, project schedule, and network diagram.
Project schedule, resource estimates, progress reports, and change requests.
Scope management plan, project network diagram, constraints, and assumptions.
Schedule management plan, scope baseline, enterprise environmental factors, and organizational process assets.
Create a free account and access millions of resources
Similar Resources on Quizizz
19 questions
Quiz 3 - Project Management

Quiz
•
University
20 questions
Exam - Business and Financial Project Management

Quiz
•
University
20 questions
Software Engineering

Quiz
•
University
20 questions
Software Development Quiz

Quiz
•
University
18 questions
Energy Production During Exercise

Quiz
•
9th Grade - University
26 questions
Quiz 1 - ISPM2 3B

Quiz
•
University
20 questions
Company Meetings Quiz

Quiz
•
2nd Grade - University
20 questions
Project Management POP Quiz 1

Quiz
•
University
Popular Resources on Quizizz
15 questions
Character Analysis

Quiz
•
4th Grade
17 questions
Chapter 12 - Doing the Right Thing

Quiz
•
9th - 12th Grade
10 questions
American Flag

Quiz
•
1st - 2nd Grade
20 questions
Reading Comprehension

Quiz
•
5th Grade
30 questions
Linear Inequalities

Quiz
•
9th - 12th Grade
20 questions
Types of Credit

Quiz
•
9th - 12th Grade
18 questions
Full S.T.E.A.M. Ahead Summer Academy Pre-Test 24-25

Quiz
•
5th Grade
14 questions
Misplaced and Dangling Modifiers

Quiz
•
6th - 8th Grade