1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What does the term contingency mean?
Time in a project plan that has no tasks assigned. Used if tasks are not completed on time.
Shows what task is dependent on another, what task has to be completed before another can be completed
The things needed to complete the project, could include software and hardware
A given point in time when a task is expected to be started or completed
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What does the term workflow mean?
Time in a project plan that has no tasks assigned. Used if tasks are not completed on time.
Shows what task is dependent on another, what task has to be completed before another can be completed and which tasks can be completed at the same time.
The things needed to complete the project, could include software and hardware
A given point in time when a task is expected to be started or completed
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What does the term milestone mean?
Time in a project plan that has no tasks assigned. Used if tasks are not completed on time.
Shows what task is dependent on another, what task has to be completed before another can be completed and which tasks can be completed at the same time.
The things needed to complete the project, could include software and hardware
A given point in time when a task is expected to be started or completed
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What does the term resource mean?
Time in a project plan that has no tasks assigned. Used if tasks are not completed on time.
Shows what task is dependent on another, what task has to be completed before another can be completed and which tasks can be completed at the same time.
The things needed to complete the project, could include software and hardware
A given point in time when a task is expected to be started or completed
5.
MULTIPLE SELECT QUESTION
30 sec • 1 pt
Identify TWO tasks that are carried out during the planning phase
Define constraints
Create test plans
Produce user documentation
Test the final product
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Identify the phase of the project life cycle in which user documentation is created
Initiation
Planning
Execution
Evaluation
7.
MULTIPLE SELECT QUESTION
30 sec • 1 pt
What are 2 advantages of following a project life cycle
Provides a structured approach and allows everyone to see how project is progressing
There are defined inputs and outputs for each phase
It will mean that you will never run out of money or time
You won't have to return to a phase once it has been completed or you have moved on to the next phase
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?