Unit 3 Test 2 of 2
Flashcard
•
Business
•
9th - 12th Grade
•
Practice Problem
•
Hard
Wayground Content
FREE Resource
Student preview

14 questions
Show all answers
1.
FLASHCARD QUESTION
Front
The Work Breakdown Structure can BEST be thought of as an effective aid for __________ communications.
Back
Stakeholder
2.
FLASHCARD QUESTION
Front
During project executing, a team member comes to project manager because he is not sure of what work needs to be accomplished on the project. Which document contains the detailed description of work packages?
Back
WBS dictionary.
3.
FLASHCARD QUESTION
Front
Completion of a product scope is measured against: Product Management Plan, Project Management Plan, WBS & WBS Dictionary, Product Requirements
Back
WBS & WBS Dictionary
4.
FLASHCARD QUESTION
Front
You are creating your WBS and find that you keep decomposing tasks into smaller and smaller units. How can you tell when you are done?
Back
Keep decomposing tasks until you reach an amount of work that is small enough to reliably estimate required resources and duration.
5.
FLASHCARD QUESTION
Front
Decomposition is an important tool used to
Back
Create WBS
6.
FLASHCARD QUESTION
Front
What is the lowest level of WBS components known as?
Back
Work Package
7.
FLASHCARD QUESTION
Front
Which of the following is the KEY output of Verify Scope process? A more complete Scope management plan. Customer acceptance of project deliverables. Improved Schedule estimates. An improved Project management information system
Back
Customer acceptance of project deliverables.
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?