PM 1 4.01-4.03 Practice Assessment
Flashcard
•
Computers
•
9th - 10th Grade
•
Practice Problem
•
Hard
Wayground Content
FREE Resource
Student preview

14 questions
Show all answers
1.
FLASHCARD QUESTION
Front
Which of the following may generate a milestone list: Define Activities, Sequence Activities, None of these answers, Estimate Activity Durations
Back
Define Activities
2.
FLASHCARD QUESTION
Front
Reserve Analysis is a technique for: Estimate Activity Durations, Define Schedule, Sequence Activities, None of the answers
Back
Estimate Activity Durations
3.
FLASHCARD QUESTION
Front
What-if scenario analysis is done as a part of which process: Develop Schedule, Sequence Activities, Define Activities, Control Schedule?
Back
Develop Schedule
4.
FLASHCARD QUESTION
Front
Resource Leveling is a technique for: Develop Schedule, Gold Plating, Scope Baseline, Estimate Activity Durations
Back
Develop Schedule
5.
FLASHCARD QUESTION
Front
Resource reallocation from non-critical to critical activities is an example of which Project Scheduling technique?
Back
Resource Leveling
6.
FLASHCARD QUESTION
Front
To crash a schedule you should: Put extra resources on those tasks that are on the critical path.
Back
Put extra resources on those tasks that are on the critical path.
7.
FLASHCARD QUESTION
Front
A project manager is identifying and documenting relationships among the project activities of an IT project. He is undertaking which process?
Back
Sequence Activities
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?